Exam 5: Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project starts out as which of the following?

(Multiple Choice)
4.8/5
(80)

Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.

(True/False)
4.9/5
(86)

In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.

(True/False)
5.0/5
(77)

You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use in this situation?

(Multiple Choice)
4.9/5
(84)

The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.

(True/False)
4.9/5
(68)

Derivative projects are those which address incremental changes to products or processes.

(True/False)
4.8/5
(78)

Upper level management must decide between pure, functional, and matrix structures as ways to organize projects.

(True/False)
4.9/5
(76)

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost? Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost?

(Multiple Choice)
5.0/5
(75)

A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:   Using CPM, which activities have slack in this project? Using CPM, which activities have slack in this project?

(Multiple Choice)
4.7/5
(80)

Earned Value Management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.

(True/False)
4.9/5
(81)

For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?

(Multiple Choice)
4.9/5
(70)

Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project.

(True/False)
4.7/5
(80)

Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion.

(True/False)
4.8/5
(73)

A series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?

(Multiple Choice)
4.7/5
(71)

The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.

(True/False)
4.8/5
(79)
Showing 61 - 75 of 75
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)