Exam 4: Capacity Planning
Exam 1: Using Operations to Create Value100 Questions
Exam 2: Process Strategy and Analysis245 Questions
Exam 3: Quality and Performance195 Questions
Exam 4: Capacity Planning108 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems164 Questions
Exam 7: Project Management140 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management207 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning125 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration111 Questions
Exam 15: Supply Chain Sustainability73 Questions
Exam 16: Decision Making107 Questions
Exam 17: Waiting Lines108 Questions
Exam 18: Special Inventory Models53 Questions
Exam 19: Linear Programming86 Questions
Exam 20: Simulation54 Questions
Exam 21: Financial Analysis55 Questions
Exam 22: Acceptance Sampling Plans87 Questions
Exam 23: Measuring Output Rates106 Questions
Exam 24: Learning Curve Analysis51 Questions
Exam 25: Operations Scheduling120 Questions
Exam 26: Layout36 Questions
Select questions type
Which one of the following factors usually calls for a larger capacity cushion?
(Multiple Choice)
4.9/5
(67)
A standard work year is 2080 hours at the Luther Mill and it takes about 2 hours to fill a customer order.The manager at the mill is always concerned about employee idle time,so he aims for a capacity cushion of two percent.Last year saw 15,000 customer orders at the mill and the manager has a new Mercedes in mind as a company car,so he hopes that there is an increase of 10% in customer orders for next year.How many workers will the manager need to have at the mill next year?
(Multiple Choice)
4.9/5
(74)
An expansionist capacity strategy minimizes the risks of overexpansion due to overly optimistic demand forecasts.
(True/False)
4.9/5
(78)
Which one of the following factors usually motivates a smaller capacity cushion?
(Multiple Choice)
4.8/5
(76)
Kristen made a batch of chocolate chip cookie dough and then had to clean the utensils and mixing bowl before she made a batch of oatmeal raisin cookie dough.The time spent cleaning the bowl and utensils is an example of setup time.
(True/False)
4.7/5
(81)