Exam 12: Resource Management
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Utilization rule would begin work with project: Resource Resource Resource Project Date Rec'd Date Due 1 2 3 A Apr 2006 Oct 2006 200 0 400 B Feb 2006 Sep 2006 150 200 170 C Mar 2006 Alg 2006 0 250 200 Tan 2006 Nov 2006 150 100 0
(Multiple Choice)
4.8/5
(82)
What are the trade-offs among schedule slippage,resource utilization,and in-process inventory for a project manager in a multi-project environment?
(Essay)
4.8/5
(83)
This resource loading table shows the requirements for a five-task project that has a 42-day duration.The table is designed to reflect an early start schedule.Activity D has only one predecessor and activities C and E have two each.What differences exist between this table and the late start resource table?

(Essay)
4.9/5
(90)
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
(Multiple Choice)
4.9/5
(88)
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur? 
(Multiple Choice)
4.9/5
(83)
In a resource constrained project,the work must be finished by a certain time,or date,as efficiently as possible.
(True/False)
4.9/5
(75)
The amount of work waiting to be completed but delayed due to unavailable resources is known as:
(Multiple Choice)
4.9/5
(89)
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration? Activity Duration Predecessor WBS ID W 4 - 12 A 3 W 16 B 4 W 15 C 5 W 13 D 6 W 14 E 1 B 17 Z 7 A, E, C, D 18
(Multiple Choice)
4.7/5
(86)
Create a resource loading table and perform resource leveling on the project composed of the activities in this table.Activities listed in the table are measured in the number of eight-hour days.The maximum amount of time used per day is 16 hours.
Activity Time Predecessor 6 - 1 - 2 A, B 4 - 1 , 1 6 4 4 3 , 5 , 3
(Essay)
4.8/5
(71)
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the first day where this project exceeds the four worker maximum? Activity Activity time Workers Needed Predecessor A 10 1 4 2 7 3 4 1 8 2 9 3 , 13 1 14 2 , 13 3 10 1 , 5 2
(Multiple Choice)
4.8/5
(86)
The first step in the resource leveling process is to create the resource loading table.
(True/False)
4.8/5
(85)
What are the three types of constraints that projects face; provide examples and suggest ways to address these constraints?
(Essay)
4.9/5
(80)
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? 
(Multiple Choice)
4.8/5
(84)
Consider the project that is neatly summarized in this table.What are the top priority activity when using the most successors leveling heuristic? Activity Duration Predecessors Workers Required A 8 - 3 B 2 - 4 D 6 A 2 E 7 B 5
(Multiple Choice)
4.7/5
(82)
Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project. Activity Duration Predecessor A 5 days -- B 4 days A C 5 days A D 6 days B E 6 days C, D 6 days E
(Multiple Choice)
4.9/5
(88)
If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
(True/False)
4.9/5
(68)
It's resource leveling time at Satriale's Pork Store and management is pondering four possibilities for task splitting.Which of these activities would be the worst candidate for splitting?
(Multiple Choice)
4.8/5
(79)