Exam 12: Resource Management
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
What information is usually provided on a resource-usage calendar?
(Multiple Choice)
4.8/5
(99)
The problem of resource underutilization that a project manager faces when managing a single project disappears in the multi-project environment.
(True/False)
4.8/5
(76)
Which of these statements about resource management is BEST?
(Multiple Choice)
4.8/5
(73)
-The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?
(Multiple Choice)
4.9/5
(68)
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements? Activity Duration (days) Activity Cost Predecessor 10 140 8 64 , 12 96 6 120 14 168 12 144
(Multiple Choice)
5.0/5
(72)
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed? Activity Activity time Workers Needed Predecessor A 10 1 4 2 7 3 4 1 8 2 9 3 , 13 1 14 2 , 13 3 10 1 , 5 2
(Multiple Choice)
4.9/5
(78)
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project. Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
(Multiple Choice)
4.9/5
(87)
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements? 
(Multiple Choice)
4.9/5
(69)
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? 
(Multiple Choice)
5.0/5
(76)
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation? Activity Activity time Workers Needed Predecessor A 10 1 4 2 7 3 4 1 8 2 9 3 , 13 1 14 2 , 13 3 10 1 , 5 2
(Multiple Choice)
4.8/5
(87)
Sam and Dave have identified 9 activities that are required to complete their next project and developed a snazzy resource loading table.Since they each work 8 hours a day,they need your help to perform resource leveling on their project such that they can finish it by the close of business on Day 24.Activity float times are indicated by bracketed cells in the table.Times indicated in the table are in hours; the top row shows the day number of the project.The total hours for each day are shown in the bottom row of the table and cannot exceed 16 hours.The total resource time in any day cannot exceed 16 hours.

(Essay)
4.9/5
(77)
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
(Essay)
4.8/5
(83)
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? 
(Multiple Choice)
5.0/5
(79)
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number? Activity Duration Predecessor WBS DD 4 - 12 3 16 4 15 5 13 6 14 1 17 Z 7 ,,, 18
(Multiple Choice)
4.9/5
(86)
Resource loading charts are used to display the amount of resources required as a function of time on a graph.
(True/False)
4.8/5
(94)
All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
(True/False)
4.8/5
(75)
-Use this resource load chart to determine which activity uses the fewest resources.
(Multiple Choice)
4.8/5
(86)
-Use this resource load chart to determine which activity is the longest in duration.
(Multiple Choice)
4.9/5
(71)
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity C start under a leveled project with the four worker limitation? Activity Activity time Workers Needed Predecessor A 10 1 4 2 7 3 4 1 8 2 9 3 , 13 1 14 2 , 13 3 10 1 , 5 2
(Multiple Choice)
4.8/5
(83)
Showing 61 - 80 of 99
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)