Exam 12: Resource Management
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
If an activity can be split,only the functional portion of the original activity needs to be accomplished for the project to be fully completed.
(True/False)
4.9/5
(79)
Create a resource loading chart for the project described by this network. 
(Essay)
4.9/5
(76)
What resources have been initially over-allocated in the project described by the table? Assume that all activities will begin at their early start times and require the number of hours per day indicated in the table.Each worker is available for 8 hours per day.Do not level this project.
Activity Activity Length Predecessor Resource Resource Hours Per Day A 9 - Lisa 1 B 8 - Nathan 7 C 13 A Take 6 D 11 B Nathan 6 E 6 B Take 4 F 9 C Lisa 4 G 9 D Take 5 H 9 E Lisa 6 M 9 F, G Nathan 7 J 4 F, H Lisa 2 K 1 M, J Nathan 6 L 11 K Take 7
(Essay)
4.9/5
(68)
-Use this resource load chart to determine which activity uses the greatest number of resources.
(Multiple Choice)
4.8/5
(75)
Consider the portfolio of projects described in the table.The resource requirements are in numbers of labor hours.The Greatest Resource Demand rule would begin work with project: Resource Resource Resource Project Date Rec'd Date Due 1 2 3 A Apr 2006 Oct 2006 200 350 400 B Feb 2006 Sep 2006 125 200 100 D Mar 2006 Alg 2006 100 650 200 Tan 2006 Nov 2006 150 250 350
(Multiple Choice)
4.9/5
(98)
Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
(Multiple Choice)
4.9/5
(78)
In-process inventory represents the amount of work waiting to be completed but delayed due to unavailable resources.
(True/False)
4.9/5
(70)
What is mathematical programming,how can it be applied to resource decisions,and what are the advantages and disadvantages of doing so?
(Essay)
4.9/5
(82)
The process that addresses the complex challenges of project constraints is known as:
(Multiple Choice)
4.8/5
(81)
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule.
Activity Activity time Activity Cost Predecessor 10 140 8 64 , 12 96 6 120 14 168 12 144
(Essay)
4.8/5
(74)
The amounts of individual resources that a schedule requires during specific time periods is referred to as the resource's:
(Multiple Choice)
4.8/5
(74)
There is,for almost all projects,usually a dominant constraint that serves as the final arbiter of project decisions.
(True/False)
4.9/5
(90)
Describe resource leveling; its objectives and the basic five-step technique to perform it.
(Essay)
4.8/5
(78)
Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic? Activity Duration Predecessors Workers Required A 2 - 3 B 4 A 4 D 6 A 2 E 7 B 5
(Multiple Choice)
4.9/5
(64)
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? Activity Duration Predecessor 5 days - 4 days 5 days A 6 days 6 days , 6 days
(Multiple Choice)
4.8/5
(85)
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks? Activity Duration Predecessor WBS ID W 4 - 12 A 3 W 16 B 4 W 15 C 5 W 13 D 6 W 14 E 1 B 17 Z 7 A, E, C, D 18
(Multiple Choice)
4.9/5
(79)
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
Activity Activity time Activity Cost Predecessor 10 140 8 64 , 12 96 6 120 14 168 12 144
(Essay)
4.9/5
(90)
-The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:
(Multiple Choice)
4.7/5
(76)
Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times.

(Essay)
4.8/5
(78)
Showing 41 - 60 of 99
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)