Exam 5: Job-Order Costing
Exam 1: Introduction to Managerial Accounting64 Questions
Exam 2: Basic Managerial Accounting Concepts247 Questions
Exam 3: Cost Behavior237 Questions
Exam 4: Cost-Volume-Profit Analysis: a Managerial Planning Tool179 Questions
Exam 5: Job-Order Costing196 Questions
Exam 6: Process Costing177 Questions
Exam 7: Activity-Based Costing and Management178 Questions
Exam 8: Absorption and Variable Costing, and Inventory Management124 Questions
Exam 9: Profit Planning186 Questions
Exam 10: Standard Costing: a Managerial Control Tool180 Questions
Exam 11: Flexible Budgets and Overhead Analysis172 Questions
Exam 12: Performance Evaluation and Decentralization166 Questions
Exam 13: Short-Run Decision Making: Relevant Costing170 Questions
Exam 14: Capital Investment Decisions172 Questions
Exam 15: Statement of Cash Flows185 Questions
Exam 16: Financial Statement Analysis191 Questions
Select questions type
Which of the following is true about the job-order cost sheet?
(Multiple Choice)
5.0/5
(61)
Match each item with the correct statement below.
-A single overhead rate calculated using all estimated overhead for a factory divided by the estimated activity level across the entire factory
(Multiple Choice)
4.9/5
(73)
the costs of job are transferred from the work-in-process account to finished goods account
(Multiple Choice)
4.9/5
(83)
Figure 5-11.Olson Corporation constructs new homes. Assume that Olson uses a job costing system. During May of the current year, the following transactions occurred:
Olson purchased $4,500 of lumber on account.Olson used $3,750 of lumber in production and incurred 50 hours of direct labor hours at $15 per hour.Depreciation of $1,500 on equipment used to build new houses was recorded.A house that was completed last period at a cost of $150,000 was sold for $180,000 in cash.
-Refer to Figure 5-11. The journal entry to record labor for Olson would include a
(Multiple Choice)
4.8/5
(81)
Figure 5-8.John's Water Slides makes custom water slides for hotels. On September 1, there were three jobs in process, Jobs 812, 813, and 814. Two more jobs were started during September, Jobs 815 and 816. By September 30, Jobs 812, 814, and 816 were finished. The following data has been collected:
Overhead is applied at the rate of 120% of direct labor cost. Jobs are sold at cost plus 60%. Selling and administrative expenses for September totaled $2,950. By September 30, Jobs 812 were 816 are sold, but the customer who ordered Job 814 decided he did not want the slide so it is still in the warehouse.
-Refer to Figure 5-8. Calculate the ending balance in Work-in-Process as of September 30.
(Multiple Choice)
4.9/5
(72)
On February 1, Job 12 had a beginning balance of $200. During February, direct materials of $500 and direct labor of $200 were added to the job. Overhead is applied to production at a rate of 55% of direct labor. There are 5 units in Job 12. What is the unit cost?
(Multiple Choice)
4.8/5
(80)
Manufacturing and service firms producing unique products or services require job-order accounting systems.
(True/False)
4.9/5
(65)
Figure 5-9.Warwick Company has the following transactions for the month of September:
Balances at the beginning of the month were:
-Refer to Figure 5-9. What is the correct journal entry to record actual overhead for the month?

(Short Answer)
4.9/5
(76)
Bower Company manufactures a product in a factory that has two producing departments, Cutting and Stitching, and two support departments, D1 and D2. The activity driver for D1 is number of employees, and the activity driver for D2 is number of machine hours. The following data pertain to Bower:
Required:
A. Calculate the cost assignment ratios to be used under the direct method for departments D1 and D2.
B. Allocate the support department costs to the producing departments by using the direct method.
(Essay)
4.8/5
(83)
Which of the following is not true about job-order costing?
(Multiple Choice)
4.7/5
(83)
Which of the following is not a characteristic of job-order costing?
(Multiple Choice)
4.9/5
(87)
In an actual cost system, actual direct materials, actual direct labor and estimated overhead are used to determine unit cost.
(True/False)
4.8/5
(87)
Departmental overheads cannot be added together to get plantwide overhead.
(True/False)
4.9/5
(74)
If actual overhead is greater than applied overhead, the variance is called underapplied overhead.
(True/False)
4.7/5
(87)
Using normal costing, which costs never enter the work-in-process account?
(Multiple Choice)
4.8/5
(90)
Which form asks for type, quantity, unit price of direct materials issued, and for the number of the job?
(Multiple Choice)
4.9/5
(92)
When the work-in-process account is debited for direct labor, what account is usually credited?
(Multiple Choice)
4.7/5
(67)
Figure 5-8.John's Water Slides makes custom water slides for hotels. On September 1, there were three jobs in process, Jobs 812, 813, and 814. Two more jobs were started during September, Jobs 815 and 816. By September 30, Jobs 812, 814, and 816 were finished. The following data has been collected:
Overhead is applied at the rate of 120% of direct labor cost. Jobs are sold at cost plus 60%. Selling and administrative expenses for September totaled $2,950. By September 30, Jobs 812 were 816 are sold, but the customer who ordered Job 814 decided he did not want the slide so it is still in the warehouse.
-Refer to Figure 5-8. What is John's operating income for the month of September?
(Multiple Choice)
4.9/5
(77)
Figure 5-2.At the beginning of the year, Kyla Inc. estimated that overhead would be $880,000 and direct labor hours would be 220,000. At the end of the year, actual overhead was $920,600 and there were actually 230,000 direct labor hours.
-Refer to Figure 5-2. What is the predetermined overhead rate?
(Multiple Choice)