Exam 6: Project Schedule Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

 After reviewing the project management plan, project charter, enterprise environmental factors, and organizational process assets, the project team uses expert judgment, analytical techniques, and meetings to develop the _____.

(Short Answer)
4.9/5
(80)

 In project schedule management, the next step after sequencing activities is to define these activities.

(True/False)
4.9/5
(77)

 A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

(True/False)
4.8/5
(79)

 What is a network diagram? Describe two network diagramming methods.

(Essay)
4.9/5
(80)

 Knowing the amount of float allows project managers to know whether a project schedule is flexible.

(True/False)
4.8/5
(75)

 The final process in project schedule management is developing the schedule.

(True/False)
5.0/5
(84)

 A(n) _____ for a project is the series of activities that determine the earliest time by which the project can be completed.

(Short Answer)
4.7/5
(97)

 What is the latest possible time an activity might begin without delaying the project finish date?

(Multiple Choice)
4.7/5
(89)

 In a network diagram, a(n) _____ is the starting and ending point of an activity.

(Short Answer)
4.9/5
(77)

 A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

(True/False)
4.9/5
(87)

 Which network diagramming technique uses boxes to represent activities?

(Multiple Choice)
4.7/5
(90)

 In project schedule management, which process primarily involves checking and managing changes to the project schedule?

(Multiple Choice)
4.9/5
(84)

 A drawback of using _____ or sample files is that managers and their teams might rely heavily on them and ignore unique concerns for their particular projects.

(Short Answer)
4.8/5
(88)

 It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.

(True/False)
4.8/5
(92)

 A(n) _____ determines the early start and early finish dates for each activity in a project.

(Short Answer)
4.9/5
(84)

 List and briefly describe the main processes involved in project schedule management.

(Essay)
4.9/5
(79)

 Start-to-finish relationships are the most frequently used dependencies between activities.

(True/False)
4.9/5
(93)

 Which law states that work expands to fill the time allowed?

(Multiple Choice)
4.9/5
(73)

 Which is a similarity between scope control and schedule control?

(Multiple Choice)
4.9/5
(75)
Showing 81 - 99 of 99
close modal