Exam 6: Project Schedule Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

 What is the Theory of Constraints? Describe critical chain scheduling, an application of the Theory of Constraints.

(Essay)
4.7/5
(85)

 Duration estimates can be provided as a discrete number, a range, or as a(n) _____.

(Short Answer)
4.9/5
(77)

 During which relationship is the "from" activity unable start until the "to" activity is started?

(Multiple Choice)
4.8/5
(82)

 Where would a draft schedule for a project most likely be found?

(Multiple Choice)
4.9/5
(86)

 Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?

(Multiple Choice)
4.9/5
(91)

 SMART criteria are guidelines suggesting that milestones should be _____.

(Short Answer)
4.8/5
(79)

 A white diamond on a Tracking Gantt chart represents a(n) _____.

(Short Answer)
4.8/5
(77)

 Milestones are easy to achieve and are always achieved through one main activity.

(True/False)
4.8/5
(66)

 In project schedule management, the primary output of defining activities is a schedule management plan.

(True/False)
4.8/5
(76)

 Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

(Multiple Choice)
4.9/5
(91)

 In project schedule management, the ultimate goal of which process is to provide a basis for monitoring project progress for the time dimension of the project?

(Multiple Choice)
5.0/5
(78)

 In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

(True/False)
4.7/5
(77)

 To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.

(True/False)
4.8/5
(81)

 A merge occurs when one node precedes multiple nodes.

(True/False)
4.9/5
(83)

 Critical chain scheduling assumes that resources multitask and maximizes multitasking.

(True/False)
4.9/5
(82)

 _____ involves the processes required to ensure timely completion of a project.

(Short Answer)
4.8/5
(76)

 In a critical path analysis, the shortest path is what drives the completion date for the project.

(True/False)
4.9/5
(84)

 Which is true of dummy activities?

(Multiple Choice)
4.8/5
(76)

 Which statement best describes the difference between an activity list and an activity attribute?

(Multiple Choice)
5.0/5
(76)

 Project schedules grow out of basic documents such as the project charter.

(True/False)
4.8/5
(81)
Showing 61 - 80 of 99