Exam 7: Managing Risk

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

(Multiple Choice)
4.9/5
(83)

The initial step in the risk management process is to

(Multiple Choice)
4.8/5
(84)

What is the difference between budget reserves and management reserves?

(Essay)
4.9/5
(73)

The probability that a risk event will occur is higher during the initial stages of a project.

(True/False)
4.9/5
(83)

When considering risk response development, passing risk to another party instead of changing it is known as ____________ the risk.

(Short Answer)
4.8/5
(69)

Risks are evaluated in terms of

(Multiple Choice)
4.8/5
(79)

Identify and briefly describe the four ways to respond to identified risks.

(Essay)
4.8/5
(80)

Risk management is a reactive approach that is designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized.

(True/False)
4.7/5
(69)

This response is used when an identified Opportunity is not actively pursued.

(Multiple Choice)
4.9/5
(75)

The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following?

(Multiple Choice)
4.8/5
(81)

The significance of a risk is assessed in terms of the ________ and the impact of the event.

(Short Answer)
4.8/5
(67)

After your team has successfully identified potential risks that could affect the project, what is the next step?

(Multiple Choice)
4.8/5
(78)

Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.

(Multiple Choice)
4.9/5
(84)

When considering risk management, what is an opportunity? List and briefly describe 4 different responses to an opportunity.

(Essay)
4.9/5
(71)

A Risk Response Matrix contains all of the following EXCEPT

(Multiple Choice)
4.8/5
(83)

The risk assessment form contains all of the following EXCEPT

(Multiple Choice)
4.9/5
(87)

A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives.

(True/False)
4.9/5
(77)

A list of questions that address traditional areas of uncertainty on a project is known as a _________.

(Short Answer)
4.8/5
(79)

Change management systems involve reporting, controlling, and recording changes to the project baseline.

(True/False)
4.9/5
(62)

One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.

(True/False)
4.8/5
(91)
Showing 21 - 40 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)