Exam 13: Progress and Performance Measurement and Evaluation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In monitoring project time (schedule)performance, actual performance should be compared to

Free
(Multiple Choice)
4.7/5
(69)
Correct Answer:
Verified

C

A CPI index of 0.97 indicates that the project has spent less money than budgeted.

Free
(True/False)
4.8/5
(94)
Correct Answer:
Verified

False

The ________ variance is the difference between the earned value and the actual costs for the work completed to date.

Free
(Short Answer)
4.8/5
(68)
Correct Answer:
Verified

cost
Explanation: Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV - AC.

In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.

(True/False)
4.9/5
(79)

A CPI or SPI value less than one indicates that the project is

(Multiple Choice)
4.9/5
(77)

Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information.

(Short Answer)
4.8/5
(86)

The cost variance for a project is calculated by

(Multiple Choice)
4.8/5
(63)

Baseline project budgets are derived from time-phasing the work ________.

(Short Answer)
4.9/5
(70)

Of the following costs, which are NOT included in baseline?

(Multiple Choice)
4.8/5
(72)

Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.

(True/False)
4.9/5
(81)

Baseline project budgets are derived from

(Multiple Choice)
4.7/5
(73)

The ________ variance is the difference between the earned value to date and the baseline schedule.

(Short Answer)
4.9/5
(88)

________ is simply the percent complete times the original budget.

(Short Answer)
4.9/5
(83)

A reason that the duration on a task may differ from an original duration on a Tracking Gantt chart could be

(Multiple Choice)
4.9/5
(90)

Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.

(True/False)
4.8/5
(67)

A project manager would be glad to see a TCPI of 1.07.

(True/False)
4.8/5
(70)

Causes for Scope Creep can include

(Multiple Choice)
4.9/5
(81)

For a more complex project, statistical analysis can be applied to a Control Chart to identify potential causes of schedule deviation.

(True/False)
4.8/5
(83)

Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.

(Short Answer)
5.0/5
(86)

An SPI index of 1.22 indicates that the project is ________ of schedule.

(Short Answer)
4.8/5
(82)