Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When translated into a project network, a work package will become

Free
(Multiple Choice)
4.9/5
(84)
Correct Answer:
Verified

B

What is the Concurrent Engineering Approach and why should project managers be aware of it?

Free
(Essay)
4.9/5
(71)
Correct Answer:
Verified

The chainlike sequence of finish-to-start relationships is replaced by a series of start-to-start lag relationships as soon as meaningful work can be initiated for the next phase.The resulting overlap of tasks slightly increases risk but results in a much shorter schedule.

The critical path in a project network is the

Free
(Multiple Choice)
4.9/5
(73)
Correct Answer:
Verified

B

How does the WBS differ from the project network? How are WBS and project networks linked?

(Essay)
4.9/5
(88)

A _________ activity is one that has more than one activity taking place at the same time.

(Multiple Choice)
4.7/5
(89)

An activity that has more than one dependency arrow flowing into it is termed a(n)

(Multiple Choice)
4.8/5
(77)

A(n)_________ activity has more than one dependency arrow flowing from it.

(Multiple Choice)
4.8/5
(71)

The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project.

(True/False)
5.0/5
(74)

Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).

(True/False)
4.8/5
(74)

If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.

(True/False)
4.8/5
(65)

The amount of delay within a task that will not delay the overall project is known as a

(Multiple Choice)
4.9/5
(76)

Which of the following represents an activity on an activity-on-node (AON)project network?

(Multiple Choice)
4.8/5
(90)

A project network provides the basis for ________________________________ .

(Multiple Choice)
4.9/5
(82)

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?

(Multiple Choice)
4.7/5
(78)

In developing a project network, neither looping nor conditional statements are permitted.

(True/False)
4.8/5
(83)

Activities which can take place at the same time are termed

(Multiple Choice)
4.8/5
(82)

________ activities must be completed immediately before a particular activity.

(Multiple Choice)
5.0/5
(77)

The longest path through a project network is called the _________.

(Short Answer)
4.8/5
(86)

After the total slack for each activity is identified, the project manager can more easily identify the __________________.

(Multiple Choice)
4.9/5
(70)

What is a hammock activity and give an example?

(Essay)
4.9/5
(91)