Question 41
Multiple Choice
The exposure a firm opens itself to when developing a project that requires a large up-front investment can be classified as:
Question 42
Essay
What are the basic qualitative methods for identifying risk factors? What are the advantages and disadvantages of each method?
Question 43
Essay
How do mentoring and cross-training mitigate risk?
Question 44
Multiple Choice
With a cost factor of 0.8,a schedule rating of 0.6,a reliability rating of 0.5,and a performance rating of 0.6,the overall consequence of failure was:
Question 45
True/False
Opportunity emerges from favorable project circumstances and risk from unfavorable events.
Question 46
Multiple Choice
What is the relationship between a project's progress and the level of budget reserves?
Question 47
Essay
What are any four common categories of risk? What is an element of each category?
Question 48
True/False
The PRAM model for risk management proposes a "pick and choose" approach to risk management.
Question 49
Essay
Your project team is interested in determining an overall risk factor for your project to develop a personal submarine constructed entirely of Popsicle sticks and wood glue.Describe how you would develop reasonable estimates for each of the probability of failure categories and each of the consequence of failure categories.
Question 50
True/False
As risk decreases in the project life cycle,opportunity increases.
Question 51
True/False
Every one of the nine phases of the PRAM methodology has a deliverable.
Question 52
Essay
What is the PRAM methodology and what are its salient features?
Question 53
Essay
Sketch the risk level and opportunity curves as a function of the project life cycle stage.Provide an example of a project from the recent business literature or your personal experience that exhibits these characteristics.Cite specific instances where the levels of opportunity,risk,and stake fluctuated.
Question 54
Multiple Choice
With a maturity risk of 0.3,a complexity risk of 0.4,and a dependency risk of 0.5,the probability of failure is:
Question 55
Multiple Choice
Your project team members do not have adequate training to complete project work and there are far fewer team members that what you need to complete your project activities according to your originally projected schedule.This situation represents an example of:
Question 56
Essay
The PostHoc Company specializes in justifying decisions that have already been made.One day they fielded a request to perform a project risk analysis and compute the risk factor for buying an investment property on St.Charles Street in the Big Easy.There was no time (and no need to be perfectly honest)to gather any data regarding the situation;all they had to do was provide an equation and a number that showed the project wasn't too risky for the investor that had already made a decision to proceed.The investor wanted the overall project risk factor to come in at an even 0.5 and also wanted all of the scores for the seven factors that make up this score to have identical values.What is the probability of failure for complexity if these two criteria are met?
Question 57
Multiple Choice
The residents of Enumclaw,Washington,live in the shadow of majestic Mount Rainier and its 26 glaciers.The Cascades form a ring of fire around the Pacific Northwest and erupt with surprising regularity,although Mount Rainier hasn't erupted on a major scale since about a thousand years ago.When it does erupt,the pyroclastic flow (a massive cloud of superheated ash and rock up to 1500 degrees Fahrenheit that can travel at speeds up to 300 miles per hour) will make Enumclaw a less pleasant place to live.City leaders have completed the:
Question 58
Multiple Choice
The overall consequence of failure was 0.4 and curiously enough,the consequence of performance is twice that of reliability;the consequence of reliability is twice that of schedule;and the consequence of schedule is twice that of cost.What is the consequence of failure cost?
Question 59
Multiple Choice
The mouse executive board meeting was drawing to a conclusion;the only way they would be able to detect the presence of the cat was to tie a bell around its tail.Under their risk management identification scheme,this would fall under: