Question 1
Multiple Choice
-Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Question 2
Multiple Choice
Use the information in the table to determine the early finish time for Activity D.
Early
Early
Late
Late
Task
Predecessor
Duration
Start
Firish
Start
Firish
A
−
−
8
B
A
14
C
A
23
8
D
C
,
B
6
23
26
E
C
32
F
D
,
E
32
38
\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}
Task
A
B
C
D
E
F
Predecessor
−
−
A
A
C
,
B
C
D
,
E
Duration
8
6
Early
Start
23
32
Early
Firish
23
32
Late
Start
14
8
26
Late
Firish
38
Question 3
Multiple Choice
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
Question 4
Essay
Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
Activity
Predecessor
Optirnistic
Likely
Pessimistic
A
−
−
5
7
10
B
A
4
6
9
C
A
10
13
18
D
B
3
11
15
E
C
,
D
2
3
5
\begin{array} { | l | l | l | l | l |} \hline \text { Activity } & \text { Predecessor } & \text { Optirnistic } & \text { Likely } & \text { Pessimistic } \\\hline \text { A } & -- & 5 & 7 & 10 \\\hline B & \text { A } & 4 & 6 & 9 \\\hline \mathrm { C } & \text { A } & 10 & 13 & 18 \\\hline \mathrm { D } & \mathrm { B } & 3 & 11 & 15 \\\hline \mathrm { E } & \mathrm { C } , \mathrm { D } & 2 & \boldsymbol { 3 } & 5 \\\hline\end{array}
Activity
A
B
C
D
E
Predecessor
−
−
A
A
B
C
,
D
Optirnistic
5
4
10
3
2
Likely
7
6
13
11
3
Pessimistic
10
9
18
15
5
Question 5
Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project is completed in 31 days?
Activity
Optimistic
time
Most Likely
time
Pessimistic
time
Predecessor
Corner Posts
4
5
6
-
String Line
7
8
9
−
Dig Holes
10
12
14
Corner Posts
Plant Posts
11
14
17
String Line
Weld Top Bar
8
11
14
String Line
Dig Holes, Plant
Paint
9
11
13
Posts
Tack Wire
9
12
16
Weld Top Bar
\begin{array}{|l|l|l|l|l|}\hline \text { Activity } & \begin{array}{l}\text { Optimistic } \\\text { time }\end{array} & \begin{array}{l}\text { Most Likely } \\\text { time }\end{array} & \begin{array}{l}\text { Pessimistic } \\\text { time }\end{array} & \text { Predecessor } \\\hline \text { Corner Posts } & 4 & 5 & 6 & \text { - } \\\hline \text { String Line } & 7 & 8 & 9 & - \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 & 12 &16& \text { Weld Top Bar } \\\hline\end{array}
Activity
Corner Posts
String Line
Dig Holes
Plant Posts
Weld Top Bar
Paint
Tack Wire
Optimistic
time
4
7
10
11
8
9
9
Most Likely
time
5
8
12
14
11
11
12
Pessimistic
time
6
9
14
17
14
13
16
Predecessor
-
−
Corner Posts
String Line
String Line
Dig Holes, Plant
Posts
Weld Top Bar
Question 6
Essay
Use the information in the table to sketch the network and compute early and late start times.
Activity
Time
Predecessor
A
8
B
4
A
C
5
B
,
F
D
12
A
E
8
D
F
4
D
G
9
E
,
F
\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 8 & \\\hline\mathrm { B} & 4 & \text { A } \\\hline \mathrm { C } & 5 & \mathrm {~B} , \mathrm {~F} \\\hline \mathrm { D } & 12 & \mathrm {~A} \\\hline \mathrm { E } & 8 & \mathrm { D } \\\hline \mathrm { F } & 4 & \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline\end{array}
Activity
A
B
C
D
E
F
G
Time
8
4
5
12
8
4
9
Predecessor
A
B
,
F
A
D
D
E
,
F
Question 7
Multiple Choice
Based on the activity network pictured,what is the BEST statement?
Question 8
Multiple Choice
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?
Question 9
True/False
A merge activity has two or more immediate predecessors.
Question 10
True/False
The PERT technique assumes that durations are more deterministic.
Question 11
Essay
Compute early and late start and finish times for the network shown.
Question 12
True/False
Float is always measured in exactly the same way as slack.
Question 13
Multiple Choice
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?
Question 14
Multiple Choice
What is the slack time for Activity D given the activity times and precedence requirements shown in the table?
Activity
Time
Predecessor
A
5
−
−
B
7
−
−
C
8
A
D
7
A
E
4
B
F
8
C
,
D
G
9
E
,
F
H
7
G
\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}
Activity
A
B
C
D
E
F
G
H
Time
5
7
8
7
4
8
9
7
Predecessor
−
−
−
−
A
A
B
C
,
D
E
,
F
G
Question 15
True/False
The late start time should be calculated using a forward pass through the network.
Question 16
Multiple Choice
What is the slack time for Activity B given the activity times and precedence requirements shown in the table?
Activity
Time
Predecessor
A
5
−
−
B
7
−
−
C
8
A
D
7
A
E
4
B
F
8
C
,
D
G
9
E
,
F
H
7
G
\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 5 & - - \\\hline \mathrm {B} & 7 &- - \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \mathrm {~A} \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 9 & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}
Activity
A
B
C
D
E
F
G
H
Time
5
7
8
7
4
8
9
7
Predecessor
−
−
−
−
A
A
B
C
,
D
E
,
F
G
Question 17
Multiple Choice
Use the information in the table to determine the late finish time for Activity B.
Early
Early
Late
Late
Task
Predecessor
Duration
Start
Firish
Start
Firish
A
−
−
8
B
A
14
C
A
23
8
D
C
,
B
6
23
26
E
C
32
F
D
,
E
32
38
\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}
Task
A
B
C
D
E
F
Predecessor
−
−
A
A
C
,
B
C
D
,
E
Duration
8
6
Early
Start
23
32
Early
Firish
23
32
Late
Start
14
8
26
Late
Firish
38
Question 18
Multiple Choice
Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity?
Question 19
Multiple Choice
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?