Exam 7: Project Management
Exam 1: Using Operations to Create Value100 Questions
Exam 2: Process Strategy and Analysis245 Questions
Exam 3: Quality and Performance195 Questions
Exam 4: Capacity Planning108 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems164 Questions
Exam 7: Project Management140 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management207 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning125 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration111 Questions
Exam 15: Supply Chain Sustainability73 Questions
Exam 16: Decision Making107 Questions
Exam 17: Waiting Lines108 Questions
Exam 18: Special Inventory Models53 Questions
Exam 19: Linear Programming86 Questions
Exam 20: Simulation54 Questions
Exam 21: Financial Analysis55 Questions
Exam 22: Acceptance Sampling Plans87 Questions
Exam 23: Measuring Output Rates106 Questions
Exam 24: Learning Curve Analysis51 Questions
Exam 25: Operations Scheduling120 Questions
Exam 26: Layout36 Questions
Select questions type
Table 7.4
-Using Table 7.4,what is the early start time for activity D?
(Multiple Choice)
4.8/5
(81)
Using Table 7.5,every day the construction crew is on-site costs $1000.What activities would you consider crashing to reduce the project completion cost?
(Multiple Choice)
4.7/5
(83)
Which one of the following conditions violates the assumptions of PERT/CPM networks?
(Multiple Choice)
4.9/5
(86)
The normal cost is the amount of money it normally takes to complete an activity faster than its normal time.
(True/False)
4.7/5
(80)
The phase of project management that takes the most resources is the execution phase.
(True/False)
4.9/5
(86)
In making an estimate of the most pessimistic time for an activity,a manager deliberately estimates this time too high (i.e. ,longer than it should be).What is the result of this action,assuming the beta distribution is being used to make time estimates?
(Multiple Choice)
4.8/5
(77)
A relationship that determines the sequence for undertaking activities is a precedence relationship.
(True/False)
4.7/5
(91)
Information accuracy relative to the completeness of the work breakdown structure and communication of timely information affect the:
(Multiple Choice)
4.9/5
(85)
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 7.14,if the expected time for activity C is changed to 12 weeks,by how many weeks will the project's expected completion time increase?
(Multiple Choice)
4.7/5
(75)
The following table contains a list of activities,with precedence requirements and crash costs.All start and finish times and crash costs are on a per-week basis.
a.Determine the project cost and duration without crashing.
b.Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
c.Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
d.Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.

(Essay)
5.0/5
(86)
The optimistic time is the probable time required to perform the activity.
(True/False)
4.7/5
(79)
Table 7.9
-Using Table 7.9,what is the minimum time schedule for this project?
(Multiple Choice)
4.8/5
(81)
A Gantt chart is a project schedule that superimposes project activities on a time line.
(True/False)
4.9/5
(72)
Table 7.8
-Using Table 7.8,what is the critical path for this project using the normal times?
(Multiple Choice)
4.9/5
(80)
A(n)________ identifies the key threats to a project and prescribes ways to work around them.
(Essay)
4.9/5
(85)
Table 7.13
All activity times for the project are in weeks.
-Using Table 7.13,what is the critical path of this project?
(Multiple Choice)
4.7/5
(86)
Table 7.8
-Using Table 7.8,what is the latest start time for activity E?
(Multiple Choice)
4.8/5
(86)
Fig.7.1
-For the network shown in Fig.7.1,which of the following is the critical path?
(Multiple Choice)
4.9/5
(74)
Table 7.4
-Using Table 7.4,what is the largest amount of slack that any activity in the project has?
(Multiple Choice)
4.9/5
(86)
Figure to accompany Table 7.7
Table 7.7
-What is the critical path for the project shown in the above network and Table 7.7,using the normal times?
(Multiple Choice)
4.9/5
(78)