Exam 7: Project Management

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A good risk management plan will contain which of these elements?

(Multiple Choice)
4.8/5
(77)

Table 7.8 Table 7.8    -Using Table 7.8,what is the earliest possible completion time for activity E after crashing? -Using Table 7.8,what is the earliest possible completion time for activity E after crashing?

(Multiple Choice)
4.8/5
(89)

Risk is a measure of the probability and consequences of not reaching a defined project goal.

(True/False)
4.9/5
(76)

Which of these step comes first in the project life cycle?

(Multiple Choice)
4.9/5
(81)

The project manager and team can step back and examine how the project work was accomplished during the ________ phase of the project.

(Essay)
4.9/5
(77)

A company could add $10,000 per week in revenues if the project depicted in Table 7.10 could be shortened. Table 7.10 A company could add $10,000 per week in revenues if the project depicted in Table 7.10 could be shortened. Table 7.10   Four possible options exist to crash activities: crash A by one week at a cost of $6,000;crash C by two weeks at a cost of $15,000;crash E by one week at a cost of $2,000;and crash I one week at a cost of $7,000.What is the maximum amount of additional profit that can be made by crashing an option (or options)? Four possible options exist to crash activities: crash A by one week at a cost of $6,000;crash C by two weeks at a cost of $15,000;crash E by one week at a cost of $2,000;and crash I one week at a cost of $7,000.What is the maximum amount of additional profit that can be made by crashing an option (or options)?

(Multiple Choice)
4.9/5
(72)

Table 7.8 Table 7.8    -Using Table 7.8,what is the activity with the greatest amount of slack? -Using Table 7.8,what is the activity with the greatest amount of slack?

(Multiple Choice)
4.8/5
(70)

Table 7.6 Table 7.6    -Using Table 7.6,what is the latest start time for activity A? -Using Table 7.6,what is the latest start time for activity A?

(Multiple Choice)
4.9/5
(79)

Table 7.2 Table 7.2   -Using Table 7.2,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase? -Using Table 7.2,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?

(Multiple Choice)
4.7/5
(67)

A(n)________ is an interrelated set of activities that has a definite starting and ending point and that results in a unique outcome for a specific allocation of resources.

(Essay)
4.9/5
(79)

Scope creep is one of the primary causes of project failure.

(True/False)
4.8/5
(85)

Disaster strikes and activity F takes 20 days instead of the anticipated 5 days.Using Table 7.5,how much longer will the project last than initially estimated?

(Multiple Choice)
4.8/5
(67)

Table 7.5 Table 7.5    -Using Table 7.5,what is the earliest that activity D can be finished? -Using Table 7.5,what is the earliest that activity D can be finished?

(Multiple Choice)
4.9/5
(73)

Table 7.4 Table 7.4    -Using Table 7.4,what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date? -Using Table 7.4,what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date?

(Multiple Choice)
4.9/5
(83)

Figure to accompany Table 7.1 Figure to accompany Table 7.1   Table 7.1    -Using the information shown in Table 7.1,what is the project duration? Table 7.1 Figure to accompany Table 7.1   Table 7.1    -Using the information shown in Table 7.1,what is the project duration? -Using the information shown in Table 7.1,what is the project duration?

(Multiple Choice)
4.9/5
(69)

Table 7.13 All activity times for the project are in weeks. Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13,if the expected time for activity H is changed to 25 weeks,by how many weeks will the project's expected completion time increase? -Using Table 7.13,if the expected time for activity H is changed to 25 weeks,by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.9/5
(88)

How many week(s)of crashing are available for activity B in Table 7.7?

(Multiple Choice)
4.8/5
(88)

What is the crashing cost per week for activity E in Table 7.7?

(Multiple Choice)
4.9/5
(79)

Table 7.3 Table 7.3   -Using Table 7.3,what is the earliest expected time of completion of the whole project? -Using Table 7.3,what is the earliest expected time of completion of the whole project?

(Multiple Choice)
4.8/5
(73)

The phase of project management that takes the most resources is the ________,during which managers focus on activities that pertain to deliverables.

(Essay)
4.8/5
(76)
Showing 21 - 40 of 140
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)