Exam 22: Acceptance Sampling Plans
Exam 1: Using Operations to Create Value100 Questions
Exam 2: Process Strategy and Analysis245 Questions
Exam 3: Quality and Performance195 Questions
Exam 4: Capacity Planning108 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems164 Questions
Exam 7: Project Management140 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management207 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning125 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration111 Questions
Exam 15: Supply Chain Sustainability73 Questions
Exam 16: Decision Making107 Questions
Exam 17: Waiting Lines108 Questions
Exam 18: Special Inventory Models53 Questions
Exam 19: Linear Programming86 Questions
Exam 20: Simulation54 Questions
Exam 21: Financial Analysis55 Questions
Exam 22: Acceptance Sampling Plans87 Questions
Exam 23: Measuring Output Rates106 Questions
Exam 24: Learning Curve Analysis51 Questions
Exam 25: Operations Scheduling120 Questions
Exam 26: Layout36 Questions
Select questions type
A single-sampling plan by attributes is needed for a purchased component.Given the following information,what is the consumer's risk? Table G.1 is appended to this exam. Sample size = 100
Acceptance number (c)= 1
Acceptance quality level (AQL )= 0.01
Lot tolerance proportion defective (LTPD)= 0.05
(Multiple Choice)
4.8/5
(73)
A double-sampling plan has a lower ________ than a single-sampling plan.
(Essay)
4.8/5
(87)
What is the basic idea of incoming inspection? Why does a producer perform it?
(Essay)
4.8/5
(73)
________ is the risk that the sampling plan will fail to verify an acceptable lot's quality and thus reject it-a type I error.
(Essay)
4.8/5
(80)
A single-sampling plan by attributes is needed for a purchased component.Given the following information,what is the consumer's risk? Table G.1 is appended to this exam. Sample size = 100
Acceptance number (c)= 1
Acceptance quality level (AQL )= 0.02
Lot tolerance proportion defective (LTPD)= 0.07
(Multiple Choice)
5.0/5
(75)
As more firms initiate total quality management systems,the need for acceptance sampling will increase.
(True/False)
4.8/5
(80)
Use Table G.1 for the following question.What is the acceptance number of a single-sampling plan if n = 300,LPTD = 0.02,and = 0.15?
(Multiple Choice)
4.8/5
(78)
A single-sampling plan by attributes is needed for a purchased component.Given the following information,what is the producer's risk? Table G.1 is appended to this exam. Sample size = 75
Acceptance number (c)= 3
Acceptance quality level (AQL )= 0.01
Lot tolerance proportion defective (LTPD)= 0.04
(Multiple Choice)
4.9/5
(79)
The AOQL is the highest point in the plot of AOQ against the percentage of defectives in the lot.
(True/False)
4.8/5
(72)
A company is developing an acceptance sampling plan to monitor quality.The acceptable quality level (AQL)is 0.01,and a sampling plan having c = 5 is being considered.If a producer's risk of 0.03 is desired,what should be the sample size? Table G.1 is appended to this exam.
(Multiple Choice)
4.7/5
(78)
A small ________ can be disregarded in AOQ calculations involving an extremely large lot size.
(Essay)
4.8/5
(87)
Champion Cooling Company has developed a sampling plan calling for a sample size of 25 and an acceptance number of 1.The proportion defective and probability of acceptance appear in the table.Floyd Electric,their supplier ships whatever Champion Cooling asks;sometimes the lot size is as small as 30 units and it has been as large as 10,000 units.Champion Cooling decides to stick with what they know,a sample size of 25 and an acceptance number of 1 despite advice to the contrary.Which statement regarding their sampling plan is BEST? 
(Multiple Choice)
4.7/5
(72)
The management of a company wishes to develop a new acceptance sampling plan that keeps acceptable quality level,lot tolerance proportion defective,and c constant.If the sample size (n)is increased,compared to the prior plan,which of the following is TRUE?
(Multiple Choice)
4.9/5
(91)
A double-sampling plan is usually less expensive than a single-sampling plan if the lot has a high number of defectives.
(True/False)
4.8/5
(69)
Relative to an acceptance sampling plan,what is the net effect of increasing n while holding c constant?
(Essay)
4.9/5
(89)
The lot tolerance proportion defective (LTPD)is the customer's desired level of quality.
(True/False)
4.8/5
(72)
________ is the risk that a lot with LTPD will be accepted-a type II error.
(Essay)
4.9/5
(87)
This OC curve represents a sampling plan developed for a lot size of 500,a sample size of 15,and an acceptance number of 2.The probability of acceptance for each of the first six points appears next to the plotted point.What is the average outgoing quality limit? 
(Multiple Choice)
4.7/5
(89)