Exam 6: Capacity Planning
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
The seven-person maintenance function at a hospital performs both preventive and corrective maintenance on hundreds of items each month.All the workers are scheduled for 40 hours per week and there are four weeks in a month.It is the goal of the maintenance department to achieve 90% utilization with a mix of two-thirds preventive maintenance and one-third corrective maintenance.How many hours each month are spent performing corrective maintenance if they achieve their 90% utilization and correct/preventive mix targets?
(Essay)
4.9/5
(87)
Table 6.7
The B.Sharp Company has a rapidly growing product line that requires two work centers,X and Y for manufacture.Work Center X has a current capacity of 50,000 units per year,and Work Center Y is capable of 55,000 units per year.This year (year 0),sales of the product line are expected to reach 50,000 units.Growth is projected at an additional 3,000 units each year through year 3.Pre-tax profits are expected to be $60 per unit throughout the 3-year planning period.Two alternatives are being considered:
-Use the information in Table 6.7.What action,if any,should the Sharp Company take?
(Multiple Choice)
5.0/5
(96)
Table 6.3
The North Bend Manufacturing Company is producing two types of products,A and B.Demand forecasts for next year and other production-related information are provided in the following table:
Both products A and B are produced at the same operation called MASAC27A.
-Using the information in Table 6.3,what is the total number of hours required for MASAC27A equipment for the next year?
(Multiple Choice)
4.9/5
(79)
Table 6.8
The Summerville Vitamin Company manufactures bottles of animal-shaped chewable vitamins for children.This product line requires two work centers,tablet manufacturing and packaging.The tablet manufacturing work center has a current capacity of 140,000 bottles per month,and packaging is capable of 100,000 units per month.This year (year 0),monthly sales of the product line are expected to reach 100,000 units.Growth per month is projected at an additional 25,000 units through year 4 (i.e. ,125,000 per month in year #1,150,000 per month in year #2,etc. ).Pre-tax profits are expected to be $5 per unit throughout the 4-year planning period.Two alternatives are being considered:
-Expand both tablet manufacturing and packaging at the end of year 0 to a capacity of 200,000 units per month,at a total cost for both work centers of $2,250,000;
(Short Answer)
4.9/5
(89)
If a system is well balanced,which one of the following changes usually calls for a smaller capacity cushion?
(Multiple Choice)
4.8/5
(74)
A well-educated operations manager used the capacity requirements equation to determine the number of crackerbox welders to purchase for the shop,given the standard time per unit,hours available per machine,among other relevant parameters.He studied the answer,12.6,and concluded that:
(Multiple Choice)
4.8/5
(81)
Table 6.4
Mr.Lee is considering a capacity expansion for his supermarket.The annual sales projected for the next five years follow.The current capacity is equivalent to $300,000 sales.Assume a 20 percent pretax profit margin.
-Using the information in Table 6.4,if Lee expands the capacity to an equivalent of $360,000 sales now (year 0),how much would pretax cash flow in year 5 increase because of this expansion?
(Multiple Choice)
4.9/5
(81)
A well-educated operations manager used the capacity requirements equation to determine the number of crackerbox welders to purchase for the shop,given the standard time per unit,hours available per machine,among other relevant parameters.He studied the answer,2.2,and concluded that:
(Multiple Choice)
4.8/5
(80)
Table 6.6
Burdell Labs is a diagnostic laboratory that does various tests (blood tests,urine tests,etc. )for doctors' offices in the Indianapolis area.Test specimens are picked up at the doctors' offices and are transported to the testing facility,with uniform arrivals throughout the day.All tests go through two testing centers in the testing facility,Test Center A and Test Center B.A has a current capacity of 1,000 units per week,and B is capable of 1,500 units per week.The facility operates 50 weeks per year.This year (year 0),test volumes are expected to reach 1,000 units per week.Growth per week is projected at an additional 200 units through year 5 (i.e. ,1,200 per week in year #1,1,400 per week in year #2,etc. ).Pre-tax profits are expected to be $5 per test throughout the 5-year planning period.Two alternatives are being considered:
-Use the information in Table 6.6.What is the pre-tax cash flow (net present value)for alternative #2 compared to the base case of doing nothing for the next five years?
(Multiple Choice)
4.8/5
(76)
The Northern Manufacturing Company is producing products A and B,using the same machine called MASAC27A.Demand forecasts for next year and other production-related information are provided in the following table.
The company works 250 days per year and operates 2 shifts each day,each shift covering 8 hours.If 25 percent of capacity cushion is maintained throughout the year,how many machines (MASAC27A)does the company need next year to meet the demand? (Round your answer up to the next whole machine. )
(Multiple Choice)
4.8/5
(79)
The seven-person maintenance function at a hospital performs both preventive and corrective maintenance on hundreds of items each month.All the workers are scheduled for 40 hours per week and there are four weeks in a month.It is the goal of the maintenance department to achieve 90% utilization with a mix of two-thirds preventive maintenance and one-third corrective maintenance.How many hours each month are spent performing preventive maintenance if they achieve their 90% utilization and correct/preventive mix targets?
(Essay)
4.8/5
(86)
Showing 121 - 133 of 133
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)