Exam 8: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider the following project. Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7 -Compute the slack time for activity C.

(Multiple Choice)
4.7/5
(61)

Consider the following network. Consider the following network.    -The latest start for activity 3 is ________. -The latest start for activity 3 is ________.

(Short Answer)
4.8/5
(85)

The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:

(Multiple Choice)
5.0/5
(74)

Refer to the table below to answer the question(s) that follow: ~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\ \begin{array}{c} \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\ \hline \text { A } & --- & 9 & 15 & 21 \\ \text { B } & --- & 13 & 21 & 23 \\ \text { C } & \text { A } & 6 & 9 & 18 \\ \text { D } & \text { A } & 23 & 35 & 47 \\ \text { E } & \text { B } & 19 & 26 & 27 \\ \text { F } & \text { C } & 23 & 29 & 41 \\ \text { G } & \text { D,E } & 14 & 20 & 26 \\ \text { H } & \text { F,G } & 2 & 5 & 8 \end{array} -What is the estimated standard deviation (in weeks) for the critical path completion time?

(Short Answer)
4.9/5
(92)

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:

(Multiple Choice)
4.8/5
(81)

The earliest finish time for the final activity on a project network is also the total completion of the project.

(True/False)
4.8/5
(95)

Project control involves

(Multiple Choice)
4.9/5
(82)

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor

(True/False)
4.9/5
(74)

The early start for an activity on the critical path is always equal to the earliest finish of the preceding activity.

(True/False)
4.8/5
(101)

Consider the following project. Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7 -What is the latest time that activity B can start without delaying the project?

(Multiple Choice)
4.9/5
(80)

Consider the following project. Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7 -What is the minimum possible time for completing this project?

(Multiple Choice)
4.8/5
(76)

Refer to the table below to answer the question(s) that follow: ~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\ \begin{array}{c} \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\ \hline \text { A } & --- & 9 & 15 & 21 \\ \text { B } & --- & 13 & 21 & 23 \\ \text { C } & \text { A } & 6 & 9 & 18 \\ \text { D } & \text { A } & 23 & 35 & 47 \\ \text { E } & \text { B } & 19 & 26 & 27 \\ \text { F } & \text { C } & 23 & 29 & 41 \\ \text { G } & \text { D,E } & 14 & 20 & 26 \\ \text { H } & \text { F,G } & 2 & 5 & 8 \end{array} -Within what amount of time (in weeks) is there a 90% probability that the critical path for this project will be completed?

(Short Answer)
4.9/5
(71)

The critical path activities have no slack.

(True/False)
4.8/5
(90)

Consider the following project. Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 -Determine the critical path.

(Multiple Choice)
4.9/5
(79)

A ________ shows who in the organization is responsible for doing the work in a project.

(Short Answer)
4.9/5
(82)

Refer to the table below to answer the question(s) that follow: ~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\ \begin{array}{c} \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\ \hline \text { A } & --- & 9 & 15 & 21 \\ \text { B } & --- & 13 & 21 & 23 \\ \text { C } & \text { A } & 6 & 9 & 18 \\ \text { D } & \text { A } & 23 & 35 & 47 \\ \text { E } & \text { B } & 19 & 26 & 27 \\ \text { F } & \text { C } & 23 & 29 & 41 \\ \text { G } & \text { D,E } & 14 & 20 & 26 \\ \text { H } & \text { F,G } & 2 & 5 & 8 \end{array} -What is the critical path for this project network?

(Short Answer)
4.9/5
(82)

Consider the following network. Consider the following network.    -Identify all paths in the network. -Identify all paths in the network.

(Short Answer)
4.9/5
(81)

Joe used a project management software package and has determined the following results for a given project: Expected completion time of the project = 22 days Variance of project completion time = 2.77 What is the probability of completing the project within 20 days?

(Multiple Choice)
4.9/5
(77)

Project crashing is a method for shortening the project completion time by reducing the completion time of one or more critical activities at a cost.

(True/False)
4.8/5
(66)

If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?

(Short Answer)
4.9/5
(85)
Showing 61 - 80 of 116