Exam 8: Project Management
Exam 1: Management Science121 Questions
Exam 2: Linear Programming: Model Formulation and Graphical Solution122 Questions
Exam 3: Linear Programming: Computer Solution and Sensitivity Analysis95 Questions
Exam 4: Linear Programming: Modeling Examples90 Questions
Exam 5: Integer Programming107 Questions
Exam 6: Transportation, Transshipment, and Assignment Problems98 Questions
Exam 7: Network Flow Models104 Questions
Exam 8: Project Management116 Questions
Exam 9: Multicriteria Decision Making103 Questions
Exam 10: Nonlinear Programming72 Questions
Exam 11: Probability and Statistics152 Questions
Exam 12: Decision Analysis122 Questions
Exam 13: Queuing Analysis123 Questions
Exam 14: Simulation100 Questions
Exam 15: Forecasting133 Questions
Exam 16: Inventory Management157 Questions
Exam 17: the Simplex Solution Method90 Questions
Exam 18: Transportation and Assignment Solution Methods86 Questions
Exam 19: Integer Programming: the Branch and Bound Method63 Questions
Exam 20: Nonlinear Programming: Solution Techniques55 Questions
Exam 21: Game Theory64 Questions
Exam 22: Markov Analysis64 Questions
Select questions type
Consider the following project.
Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7
-Compute the slack time for activity C.
(Multiple Choice)
4.7/5
(61)
Consider the following network.
-The latest start for activity 3 is ________.
(Short Answer)
4.8/5
(85)
The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
(Multiple Choice)
5.0/5
(74)
Refer to the table below to answer the question(s) that follow:
~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\
\begin{array}{c}
\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\
\hline \text { A } & --- & 9 & 15 & 21 \\
\text { B } & --- & 13 & 21 & 23 \\
\text { C } & \text { A } & 6 & 9 & 18 \\
\text { D } & \text { A } & 23 & 35 & 47 \\
\text { E } & \text { B } & 19 & 26 & 27 \\
\text { F } & \text { C } & 23 & 29 & 41 \\
\text { G } & \text { D,E } & 14 & 20 & 26 \\
\text { H } & \text { F,G } & 2 & 5 & 8
\end{array}
-What is the estimated standard deviation (in weeks) for the critical path completion time?
(Short Answer)
4.9/5
(92)
A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
(Multiple Choice)
4.8/5
(81)
The earliest finish time for the final activity on a project network is also the total completion of the project.
(True/False)
4.8/5
(95)
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor
(True/False)
4.9/5
(74)
The early start for an activity on the critical path is always equal to the earliest finish of the preceding activity.
(True/False)
4.8/5
(101)
Consider the following project.
Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7
-What is the latest time that activity B can start without delaying the project?
(Multiple Choice)
4.9/5
(80)
Consider the following project.
Activity Imunediate Predecessor Activity Time (drys) A -- 3 -- 4 4 6 5 , 4 7
-What is the minimum possible time for completing this project?
(Multiple Choice)
4.8/5
(76)
Refer to the table below to answer the question(s) that follow:
~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\
\begin{array}{c}
\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\
\hline \text { A } & --- & 9 & 15 & 21 \\
\text { B } & --- & 13 & 21 & 23 \\
\text { C } & \text { A } & 6 & 9 & 18 \\
\text { D } & \text { A } & 23 & 35 & 47 \\
\text { E } & \text { B } & 19 & 26 & 27 \\
\text { F } & \text { C } & 23 & 29 & 41 \\
\text { G } & \text { D,E } & 14 & 20 & 26 \\
\text { H } & \text { F,G } & 2 & 5 & 8
\end{array}
-Within what amount of time (in weeks) is there a 90% probability that the critical path for this project will be completed?
(Short Answer)
4.9/5
(71)
Consider the following project.
Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5
-Determine the critical path.
(Multiple Choice)
4.9/5
(79)
A ________ shows who in the organization is responsible for doing the work in a project.
(Short Answer)
4.9/5
(82)
Refer to the table below to answer the question(s) that follow:
~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\
\begin{array}{c}
\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\
\hline \text { A } & --- & 9 & 15 & 21 \\
\text { B } & --- & 13 & 21 & 23 \\
\text { C } & \text { A } & 6 & 9 & 18 \\
\text { D } & \text { A } & 23 & 35 & 47 \\
\text { E } & \text { B } & 19 & 26 & 27 \\
\text { F } & \text { C } & 23 & 29 & 41 \\
\text { G } & \text { D,E } & 14 & 20 & 26 \\
\text { H } & \text { F,G } & 2 & 5 & 8
\end{array}
-What is the critical path for this project network?
(Short Answer)
4.9/5
(82)
Consider the following network.
-Identify all paths in the network.
(Short Answer)
4.9/5
(81)
Joe used a project management software package and has determined the following results for a given project:
Expected completion time of the project = 22 days
Variance of project completion time = 2.77
What is the probability of completing the project within 20 days?
(Multiple Choice)
4.9/5
(77)
Project crashing is a method for shortening the project completion time by reducing the completion time of one or more critical activities at a cost.
(True/False)
4.8/5
(66)
If the early start for activity A is equal to 23 months and the duration of activity A is equal to 5 months, what is the earliest finish for activity A?
(Short Answer)