Exam 8: Project Management
Exam 1: Management Science121 Questions
Exam 2: Linear Programming: Model Formulation and Graphical Solution122 Questions
Exam 3: Linear Programming: Computer Solution and Sensitivity Analysis95 Questions
Exam 4: Linear Programming: Modeling Examples90 Questions
Exam 5: Integer Programming107 Questions
Exam 6: Transportation, Transshipment, and Assignment Problems98 Questions
Exam 7: Network Flow Models104 Questions
Exam 8: Project Management116 Questions
Exam 9: Multicriteria Decision Making103 Questions
Exam 10: Nonlinear Programming72 Questions
Exam 11: Probability and Statistics152 Questions
Exam 12: Decision Analysis122 Questions
Exam 13: Queuing Analysis123 Questions
Exam 14: Simulation100 Questions
Exam 15: Forecasting133 Questions
Exam 16: Inventory Management157 Questions
Exam 17: the Simplex Solution Method90 Questions
Exam 18: Transportation and Assignment Solution Methods86 Questions
Exam 19: Integer Programming: the Branch and Bound Method63 Questions
Exam 20: Nonlinear Programming: Solution Techniques55 Questions
Exam 21: Game Theory64 Questions
Exam 22: Markov Analysis64 Questions
Select questions type
Given the following information for a project, draw the AON (Activity-On-Node) project network.
Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5
(Essay)
4.9/5
(88)
The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days) and cost for each activity.
Activity Normal Time Crash Time Cost per day to crash A 6 6 --- B 10 8 \ 100 C 5 4 \ 300 D 4 1 \ 700 E 9 7 \ 500 F 2 1 \ 650
-Which activity should be crashed to reduce the project completion by 2 days?
(Multiple Choice)
4.9/5
(83)
A list of the tasks, broken down into modules, components, and individual tasks, is called a
(Multiple Choice)
4.9/5
(71)
Establishing precedence relationships is an element of project planning.
(True/False)
4.8/5
(86)
A dummy activity is used to show a precedence relationship, but it does not represent a
(Multiple Choice)
5.0/5
(83)
If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
(Multiple Choice)
4.8/5
(74)
In PERT, the project variance is the sum of the variance of all project activities.
(True/False)
4.9/5
(72)
Consider the following network.
-How long will it take to complete the project?
(Short Answer)
4.7/5
(84)
In PERT, the expected project completion time is assumed to be distributed according to a beta distribution.
(True/False)
4.8/5
(70)
Joe used a project management software package and has determined the following results for a given project.:
Expected completion time of the project = 22 days
Variance of project completion time = 2.77
What is the probability of completing the project over 20 days?
(Multiple Choice)
4.9/5
(98)
Refer to the table below to answer the question(s) that follow:
~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\
\begin{array}{c}
\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\
\hline \text { A } & --- & 9 & 15 & 21 \\
\text { B } & --- & 13 & 21 & 23 \\
\text { C } & \text { A } & 6 & 9 & 18 \\
\text { D } & \text { A } & 23 & 35 & 47 \\
\text { E } & \text { B } & 19 & 26 & 27 \\
\text { F } & \text { C } & 23 & 29 & 41 \\
\text { G } & \text { D,E } & 14 & 20 & 26 \\
\text { H } & \text { F,G } & 2 & 5 & 8
\end{array}
-What is the probability that the critical path for this project will be completed within 80 weeks?
(Short Answer)
4.8/5
(76)
Consider the following project.
Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5
-Determine the slack for activity F.
(Multiple Choice)
4.7/5
(83)
A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
(Multiple Choice)
4.8/5
(86)
The critical path is the ________ path through the network.
(Multiple Choice)
4.9/5
(85)
A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
(Multiple Choice)
4.8/5
(81)
Shortening the project's duration by deleting unnecessary activities is called crashing.
(True/False)