Exam 24: Standard Cost Systems
Exam 1: Accounting: Information for Decision Making118 Questions
Exam 2: Basic Financial Statements142 Questions
Exam 3: The Accounting Cycle: Capturing Economic Events150 Questions
Exam 4: The Accounting Cycle: Accruals and Deferrals131 Questions
Exam 5: The Accounting Cycle: Reporting Financial Results126 Questions
Exam 6: Merchandising Activities121 Questions
Exam 7: Financial Assets206 Questions
Exam 8: Inventories and the Cost of Goods Sold147 Questions
Exam 9: Plant and Intangible Assets147 Questions
Exam 10: Liabilities197 Questions
Exam 11: Stockholders Equity: Paid-In Capital148 Questions
Exam 12: Income and Changes in Retained Earnings133 Questions
Exam 13: Statement of Cash Flows163 Questions
Exam 14: Financial Statement Analysis146 Questions
Exam 15: Global Business and Accounting82 Questions
Exam 16: Management Accounting112 Questions
Exam 17: Job Order Cost Systems and Overhead Allocations103 Questions
Exam 18: Process Costing83 Questions
Exam 19: Costing and the Value Chain70 Questions
Exam 20: Cost-Volume-Profit Analysis121 Questions
Exam 21: Incremental Analysis97 Questions
Exam 22: Responsibility Accounting and Transfer Pricing88 Questions
Exam 23: Operational Budgeting93 Questions
Exam 24: Standard Cost Systems110 Questions
Exam 25: Rewarding Business Performance69 Questions
Exam 26: Capital Budgeting99 Questions
Exam 27: the Time Value of Money: Future Amounts and Present Values49 Questions
Exam 28: Forms of Business Organization51 Questions
Select questions type
[The following information applies to the questions displayed below.]
The Starbright Corporation has compiled the following data.The company intends to use this information to develop standard costs per unit for its single product:
Direct materials = $50 per ton
Direct labor = $12.75 per hour
Variable manufacturing overhead = $5 per direct labor hour
Fixed manufacturing overhead = $18,700
Expected production = 1,700 units
Each unit of the company's single product requires 2.5 tons of direct materials and 22.5 hours to manufacture.
-What is the standard cost for direct labor per unit for Starbright's single product? (Round your answer to the nearest dollar. )
(Multiple Choice)
4.9/5
(74)
If the actual cost per pound of direct material is less than the standard cost per pound,there is:
(Multiple Choice)
4.7/5
(83)
If the standard quantity of materials is 84,500 units at $0.15 per unit and the actual quantity is 95,000 units at $0.12 per unit,then the journal entry to record the cost of materials used includes:
(Multiple Choice)
4.7/5
(91)
Excessive overtime hours worked by direct labor workers often results in:
(Multiple Choice)
4.9/5
(92)
Standard cost system overhead variances
Rogers Manufacturing produces a component part used throughout the computer industry.Variable overhead is allocated to production at a rate of $5 per unit.The company's monthly fixed overhead costs average $30,000.Normal output levels average 40,000 units per month.During April,Rogers produced 50,000 units and incurred actual overhead costs of $280,000.
(a)Total overhead applied to production in April amounted to $________.
(b)Total overhead budgeted in April for the level of output achieved amounted to $________.
(c)April's overhead spending variance was $________ (favorable/unfavorable).
(d)April's overhead volume variance was $________ (favorable/unfavorable).
(e)For which of Rogers' two overhead variances is the production manager held responsible?
(Essay)
4.8/5
(63)
Standard cost system materials variances
Levron Corporation manufactures a line of cosmetics.The standard price of the ingredients in its beauty cream is $7 per ounce;the standard amount of material allowed per jar is 1.25 ounces.During December,5,300 jars were produced,requiring 6,784 ounces of ingredients at a total direct materials cost of $37,312.
(a)Calculate the materials price variance for December.Indicate whether it is favorable (F)or unfavorable (U).$________
(b)Who is responsible for this variance? ________
(c)Calculate the materials quantity variance for December.Indicate whether it is favorable (F)or unfavorable (U).$________
(d)What is Levron Corporation's total materials variance for December? Indicate whether it is favorable (F)or unfavorable (U).$________
(Essay)
4.9/5
(83)
The use of inexpensive,low quality,materials often results in:
(Multiple Choice)
5.0/5
(78)
In evaluating cost variances,the accounting department determines whether variances are favorable or unfavorable.
(True/False)
4.9/5
(81)
Which of the following is the most likely explanation for the types of labor variances resulting from Roman's July operations?
(Multiple Choice)
4.8/5
(63)
The purchasing manager is often included in evaluating cost variances.
(True/False)
4.7/5
(88)
Standard cost system-overhead variances
Assume the following data for John Company's August operations.
(a)Compute the amount of overhead applied to Work in Process during August.$________
(b)Compute the total manufacturing overhead budgeted based on hours worked during August.$________
(c)Compute the overhead spending variance for August.Indicate whether favorable (F)or unfavorable (U).$________
(d)Compute the overhead volume variance for August.Indicate whether favorable (F)or unfavorable (U).$________
(Essay)
4.8/5
(71)
An unfavorable cost variance will be debited to a cost variance account.
(True/False)
4.8/5
(87)
A large favorable variance from standard costs at the end of the year should be:
(Multiple Choice)
4.8/5
(90)
Controlling the materials price variance is usually the responsibility of:
(Multiple Choice)
5.0/5
(81)
Standard cost system labor variance
The following computations of March labor variances for Sam's Supply Company are incomplete.The missing items are labeled (a)through (d).If necessary,round your answers.
Labor rate variance = 4,800 hours × [(a)− $8.50] = $350 favorable
Labor efficiency variance = (b)× [5,000 hours − (c)] = $(d)
On the appropriately labeled line,identify each missing item by name (a through c)and show the missing value (a through d).Show supporting computations in the space provided.
(a)________ $________
(b)________ $________
(c)________ ________ hours
(d)$________ F or U (Circle the correct term. )
(e)During March,the supervisor left for vacation without arranging for a replacement.Which variances would have been most affected by this situation? ________
Computations
(Essay)
4.9/5
(83)
Showing 81 - 100 of 110
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)