Exam 13: Budgeting and Standard Cost Systems
Exam 1: The Role of Accounting in Business96 Questions
Exam 2: Basic Accounting Concepts89 Questions
Exam 3: Accrual Accounting Concepts111 Questions
Exam 4: Accounting for Merchandising Businesses138 Questions
Exam 5: Sarbanes-Oxley, Internal Control, and Cash110 Questions
Exam 6: Receivables and Inventories102 Questions
Exam 7: Fixed Assets and Intangible Assets86 Questions
Exam 8: Liabilities and Stockholders Equity131 Questions
Exam 9: Financial Statement Analysis83 Questions
Exam 10: Accounting Systems for Manufacturing Businesses120 Questions
Exam 11: Cost Behavior and Cost-Volume-Profit Analysis140 Questions
Exam 12: Differential Analysis and Product Pricing99 Questions
Exam 13: Budgeting and Standard Cost Systems168 Questions
Exam 14: Performance Evaluation for Decentralized Operations137 Questions
Exam 15: Capital Investment Analysis103 Questions
Select questions type
Nonmanufacturing activities are usually controlled using a static budget rather than a standard costing system.
(True/False)
4.8/5
(82)
If the price paid per unit differs from the standard price per unit for direct materials, the variance is termed:
(Multiple Choice)
4.8/5
(77)
A variable cost system is an accounting system where standards are set for each manufacturing cost element.
(True/False)
5.0/5
(79)
Which of the following formula is used to calculate direct labor rate variance?
(Multiple Choice)
4.9/5
(89)
Which of the following conditions normally would not indicate that standard costs should be revised?
(Multiple Choice)
4.8/5
(76)
If the expected sales volume for the current period is 7,000 units, the desired ending inventory is 400 units, and the beginning inventory is 300 units, the number of units set forth in the production budget, representing total production for the current period, is:
(Multiple Choice)
4.7/5
(79)
Kohlman Company began its operations on March 31 of the current year. Projected manufacturing costs for the first three months of business are $156,800, $195,200, and $217,600, respectively, for April, May, and June. Depreciation, insurance, and property taxes represent $28,800 of the estimated monthly manufacturing costs. Insurance was paid on March 31, and property taxes will be paid in November. Three-fourths of the remainder of the manufacturing costs are expected to be paid in the month in which they are incurred with the balance to be paid in the following month. Refer to the information provided for Kohlman Company. The cash payments for manufacturing in the month of May are:
(Multiple Choice)
4.9/5
(66)
Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows:
1,5501.@\ 9.10 Actual costs 1,6001.@\ 9.00 Standard costs
Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance.
(Essay)
4.7/5
(91)
The standard cost is a detailed estimate of how much a product should cost.
(True/False)
4.9/5
(67)
The formula to compute direct material quantity variance is:
(Multiple Choice)
4.9/5
(78)
If the actual direct labor hours spent producing a commodity differ from the standard hours, the variance is termed:
(Multiple Choice)
4.9/5
(60)
McCabe Manufacturing Co.'s static budget at 8,000 units of production includes $40,000 for direct labor and $4,000 for electric power. Total fixed costs are $23,000. At 9,000 units of production, a flexible budget would show:
(Multiple Choice)
4.8/5
(77)
Goal conflict can be avoided if budget goals are carefully designed for consistency across all areas of the organization.
(True/False)
4.8/5
(86)
Brown Inc.'s production budget for Product X for the year ended December 31 is as follows:
640,000 units Sales Plus desired ending inventory 725,000 Total Less estimated beginning inventory, Jan 1 Total production
In Brown's production operations, Materials A, B, and C are required to make Product X. The quantities of direct materials expected to be used for each unit of product are as follows:
Product X
Material A .50 pound per unit
Material B 1.00 pound per unit
Material C 1.20 pound per unit
The prices of direct materials are as follows:
Material A $0.60 per pound
Material B $1.70 per pound
Material C $1.50 per pound
Prepare a direct materials purchases budget for Product X.
(Essay)
4.9/5
(82)
The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows: Standard Costs 2,500 kilograms@ \8 Direct material 7,500 hours @ \1 2 Direct labor Actual Costs 2,600 kilograms@ \8 .75 Direct material 7,400 hours @ \ 11.40 Direct labor Factory overhead (100\% capacity 10,000):
Variable cost @ $2 per hour
Total variable cost, $18,000
Fixed cost @ $0.80 per hour
Total fixed cost, $8,000
The amount of the fixed factory overhead volume variance is:
(Multiple Choice)
4.9/5
(80)
Cape Corporation sells a single product. Budgeted sales for the year are anticipated to be 640,000 units, estimated beginning inventory is 98,000 units, and desired ending inventory is 80,000 units. The quantities of direct materials expected to be used for each unit of finished product are given below. \ 0.60 per pound .50. per unit Material A \ 1.70 per pound 1.00 . per unit Material \ 1.00 per pound 1.20. per unit Material C Refer to the information provided for Cape Corporation. The amount of direct material B purchased during the year is:
(Multiple Choice)
4.9/5
(72)
Following is the information about Standard Inc. The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:
Standard Costs 2,500 kilograms@ \8 Direct material 7,500 hours @ \1 2 Direct labor Actual Costs 2,600 kilograms@ \8 .75 Direct material 7,400 hours @ \ 11.40 Direct labor Factory overhead (100\% capacity 10,000):
Variable cost @ $2 per hour
Total variable cost, $18,000
Fixed cost @ $0.80 per hour
Total fixed cost, $8,000
Refer to the information provided for Standard Inc. The amount of the direct materials quantity variance is:
(Multiple Choice)
4.7/5
(82)
The budget procedure that requires all levels of management to start from zero in estimating sales, production, and other operating data is called zero-based budgeting.
(True/False)
4.9/5
(83)
If the standard to produce a given amount of product is 12,000 hours at a factory overhead rate of $5 ($3 fixed, $2 variable), actual variable factory overhead was $26,400, actual fixed factory overhead was $45,000, and 100% of productive capacity is 15,000 hours, the volume variance was $9,000 favorable.
(True/False)
4.9/5
(71)
The following data relate to direct labor costs for the current period of Executive Inc.: 6,000 hours at \1 2.00 Standard costs 7,500 hours at \ 11.60 Actual costs
Refer to the information provided for Executive Inc. What is the direct labor time variance?
(Multiple Choice)
4.9/5
(95)