Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project. Activity Average Worst-Case A 10 20 B 15 25 C 20 30 D 25 35

(Multiple Choice)