Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource.
(True/False)
4.7/5
(82)
What are some arguments against the XP technique of pair programming?
(Essay)
4.7/5
(67)
Once the organization elevates its constraint,its system has no constraint.
(True/False)
4.8/5
(83)
A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project? Activity Predecessor Length Variance A - 10 4 B A 12 3 D B 16 5 C 14 6
(Multiple Choice)
4.9/5
(75)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 20 D B 16 B A 20 E C 8 A 10 F D, E 8
(Multiple Choice)
4.7/5
(67)
A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration? 
(Multiple Choice)
4.8/5
(87)
A product backlog is the final list of what is needed to complete the project.
(True/False)
4.9/5
(84)
The waterfall project development process is well-suited for instances where:
(Multiple Choice)
4.7/5
(93)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A - 18 E C, D 13 B - 16 F C 9 C A 22 G E, F 15 D B 14
(Multiple Choice)
4.9/5
(81)
Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?
(Multiple Choice)
4.8/5
(86)
The buffers supplied to non-critical paths in critical chain project management are called:
(Multiple Choice)
4.8/5
(70)
What is Agile PM and what makes it ideal for many software development projects?
(Essay)
4.8/5
(82)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach. Activity Predecessor Length Activity Predecessor Length A - 18 E C, D 13 B - 16 F C 9 C A 22 G E, F 15 D B 14
(Multiple Choice)
4.9/5
(76)
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
(Multiple Choice)
4.9/5
(84)
Which statement about critical chain project management is BEST?
(Multiple Choice)
4.8/5
(78)
Which of the following statements about CCPM activity networks is CORRECT?
(Multiple Choice)
4.7/5
(74)
Showing 81 - 100 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)