Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource.

(True/False)
4.7/5
(82)

What are some arguments against the XP technique of pair programming?

(Essay)
4.7/5
(67)

A key element of extreme programming is:

(Multiple Choice)
4.9/5
(72)

Once the organization elevates its constraint,its system has no constraint.

(True/False)
4.8/5
(83)

A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project? Activity Predecessor Length Variance A - 10 4 B A 12 3 D B 16 5 C 14 6

(Multiple Choice)
4.9/5
(75)

A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 20 D B 16 B A 20 E C 8 A 10 F D, E 8

(Multiple Choice)
4.7/5
(67)

A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration? A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration?

(Multiple Choice)
4.8/5
(87)

A product backlog is the final list of what is needed to complete the project.

(True/False)
4.9/5
(84)

Which of these numerical (quantity)comparisons is CORRECT?

(Multiple Choice)
4.8/5
(77)

The waterfall project development process is well-suited for instances where:

(Multiple Choice)
4.7/5
(93)

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A - 18 E C, D 13 B - 16 F C 9 C A 22 G E, F 15 D B 14

(Multiple Choice)
4.9/5
(81)

CCPM advocates performing all non-critical activities:

(Multiple Choice)
4.8/5
(86)

Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?

(Multiple Choice)
4.8/5
(86)

The buffers supplied to non-critical paths in critical chain project management are called:

(Multiple Choice)
4.8/5
(70)

What is Agile PM and what makes it ideal for many software development projects?

(Essay)
4.8/5
(82)

The critical chain is usually the same as the critical path.

(True/False)
5.0/5
(81)

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach. Activity Predecessor Length Activity Predecessor Length A - 18 E C, D 13 B - 16 F C 9 C A 22 G E, F 15 D B 14

(Multiple Choice)
4.9/5
(76)

Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:

(Multiple Choice)
4.9/5
(84)

Which statement about critical chain project management is BEST?

(Multiple Choice)
4.8/5
(78)

Which of the following statements about CCPM activity networks is CORRECT?

(Multiple Choice)
4.7/5
(74)
Showing 81 - 100 of 101