Exam 7: Project Cost Management
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
____ are those costs that an organization can easily measure in dollars.
(Multiple Choice)
4.9/5
(75)
Any new technology or business process is untested and has inherent risks.
(True/False)
4.8/5
(76)
____________________ allows you to see a big-picture view of the cost of a project throughout its life cycle.
(Short Answer)
4.9/5
(83)
The ____ is the ratio of earned value to planned value and can be used to estimate the projected time to complete the project.
(Multiple Choice)
4.8/5
(85)
_________________________ and SPI less than one or less than 100 percent indicate problems.
(Short Answer)
4.8/5
(90)
Many projects,particularly information technology projects,do not have good planning information,so tracking performance against a plan might produce misleading information.
(True/False)
4.9/5
(82)
The WBS is not a required input when developing a cost estimate.
(True/False)
4.9/5
(91)
____________________ costs or benefits are costs or benefits that are difficult to measure in monetary terms.
(Short Answer)
4.8/5
(88)
The ____ is that portion of the approved total cost estimate planned to be spent on an activity during a given period.
(Multiple Choice)
4.8/5
(97)
In general,____________________ numbers for cost and schedule variance indicate problems in those areas.
(Short Answer)
5.0/5
(78)
Project managers should focus on ____,since they can control them.
(Multiple Choice)
4.9/5
(70)
Organizations have a history of spending too much money in the early phases of information technology projects.
(True/False)
4.8/5
(70)
There does not need to be a change control system to define procedures for changing the cost baseline.
(True/False)
5.0/5
(77)
When developing an estimate for a large software project,estimates cannot be made before clear system requirements have been produced.
(True/False)
4.8/5
(71)
In an earned value chart,when the actual cost line is right on or above the earned value line,costs are less than or equal to planned.
(True/False)
5.0/5
(66)
Three separate surveys of software project cost overruns found that the average cost overrun for all of the projects in their survey samples (not just unsuccessful projects)were ____ percent.
(Multiple Choice)
4.8/5
(66)
When justifying investments in new information systems and technology,the focus should only be on revenues or expenses.
(True/False)
4.8/5
(85)
____ includes the processes required to ensure that a project team completes a project within an approved budget.
(Multiple Choice)
4.7/5
(86)
Showing 81 - 100 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)