Exam 7: Project Cost Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The main outputs of the ____________________ process are a cost performance baseline,project funding requirements,and project document updates.

(Short Answer)
4.8/5
(76)

The project management plan,project funding requirements,work performance data,and organizational process assets are inputs for the process of ____.

(Multiple Choice)
4.8/5
(84)

____ allow for future situations that are unpredictable.

(Multiple Choice)
4.8/5
(61)

____ allow for future situations that may be partially planned for.

(Multiple Choice)
4.8/5
(61)

The main outputs of the ____________________ process are work performance measurements,budget forecasts,organizational process asset updates,change requests,project management plan updates,and project document updates.

(Short Answer)
5.0/5
(86)

Describe four problems with Information Technology cost estimates.

(Essay)
4.7/5
(60)

Since organizations depend on reliable information technology,there are also huge costs associated with ____.

(Multiple Choice)
5.0/5
(89)

____ involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.

(Multiple Choice)
4.7/5
(84)

If the cost performance index is less than one or less than 100 percent,the project is under budget.

(True/False)
4.8/5
(85)

Cost budgeting provides information for project funding requirements.

(True/False)
4.7/5
(75)

____ involves developing an approximation or estimate of the costs of the resources needed to complete a project.

(Multiple Choice)
4.7/5
(84)

List and briefly describe the three project cost management processes.

(Essay)
4.8/5
(78)

What are the three basic types of cost estimating? Describe each type.

(Essay)
4.8/5
(89)

The cost performance index can be used to calculate the ______________________________.

(Short Answer)
4.7/5
(84)

After you total the EV,AC,and PV data for all activities on a project,you can use the CPI and ___________________________________ to project how much it will cost and how long it will take to finish the project based on performance to date.

(Short Answer)
4.9/5
(72)

____ are costs that are not directly related to the products or services of the project,but are indirectly related to performing the project.

(Multiple Choice)
4.9/5
(92)

ROM estimates can be referred to as a ballpark estimate,a guesstimate,a swag,or a broad gauge.

(True/False)
4.9/5
(85)

Every cost estimate is unique.

(True/False)
4.8/5
(74)

A ____ is used to allocate money into an organization's budget.

(Multiple Choice)
4.9/5
(89)

Direct costs cannot be directly attributed to a certain project.

(True/False)
4.8/5
(76)
Showing 61 - 80 of 100