Exam 8: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Activities with zero slack are critical activities.

Free
(True/False)
4.8/5
(78)
Correct Answer:
Verified

True

Which of the following relationships between cost,time,and scope is not realistic?

Free
(Multiple Choice)
4.7/5
(79)
Correct Answer:
Verified

A

An activity with a duration of 8 days has an early start time of 25.Another activity has a duration of 5 days and an early start time of 25 days.Both activities precede activity M.Activity M has a duration of 4 days.What is the early start time for activity M?

Free
(Essay)
4.8/5
(75)
Correct Answer:
Verified

The first activity will have an early finish time of 33,and the other activity will have an early finish time of 30.Activity M cannot begin while either activity is still being conducted,so it can start at time 33.

This is zero for all of the first activities on a CPM network diagram.

(Multiple Choice)
4.9/5
(97)

List three project management techniques used by corporations or government.

(Essay)
4.9/5
(73)

Additional resources can rarely be used to speed up a project once it is behind schedule.

(True/False)
4.9/5
(78)

In project management,"critical activities" are activities that quality managers must be involved with.

(True/False)
4.8/5
(84)

If an activity has an optimistic time of 5 days,a pessimistic time of 10 days,and a most likely time of 8 days,what is the expected time for the activity?

(Essay)
4.8/5
(69)

A precedence relationship analysis identifies the sequence of activities defined by a work breakdown structure.

(True/False)
4.9/5
(88)

Activity 7 is directly preceded by two activities,activity 5 and activity 6.Activity 5 has an expected time of 5 and ES time of 6.Activity 6 has an expected time of 7 and an ES time of 7.Activity 7 has an expected time of 10.The ES for activity 7 is

(Multiple Choice)
5.0/5
(78)

If a project has an expected completion time of 40 days,with a standard deviation of 2 days,what is the amount of time this project will be completed in,95% of the time?

(Essay)
4.8/5
(81)

Project risk can be grouped into four categories.Which of the following is not one of the categories?

(Multiple Choice)
4.8/5
(81)

Which of the following statements accurately describes the following Gantt chart? Which of the following statements accurately describes the following Gantt chart?

(Multiple Choice)
4.8/5
(75)

In an AON network diagram,arrows can point to any direction from a node.

(True/False)
5.0/5
(81)

If an activity has an optimistic time of 5 days,a pessimistic time of 10 days,and a most likely time of 8 days,what is the variance for the activity?

(Essay)
4.9/5
(87)

Determine the amount of slack in each activity.

(Essay)
4.7/5
(81)

A contingency plan should be developed for potential problems.

(True/False)
4.8/5
(75)

Which project management tool introduces uncertainty into the project planning process?

(Multiple Choice)
4.7/5
(86)

The critical factors in project failure include all of the following except

(Multiple Choice)
4.8/5
(79)

Which of the following examples is not considered a project?

(Multiple Choice)
5.0/5
(86)
Showing 1 - 20 of 75
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)