Exam 8: Project Management
Exam 1: Operations and Supply Chain Strategy74 Questions
Exam 2: Quality Management75 Questions
Exam 3: New Product Development75 Questions
Exam 4: Process Design and Analysis75 Questions
Exam 5: Forecasting75 Questions
Exam 6: Independent Demand Inventory75 Questions
Exam 7: Dependent Demand Inventory74 Questions
Exam 8: Project Management75 Questions
Exam 9: Optimization and Simulation Modeling75 Questions
Exam 10: Capacity Planning75 Questions
Exam 11: Quality Improvement Methods75 Questions
Exam 12: Lean Enterprise75 Questions
Exam 13: Technology and Integrated Supply Management75 Questions
Exam 14: Global Supply Chain and Service Integration75 Questions
Select questions type
Activities with zero slack are critical activities.
Free
(True/False)
4.8/5
(78)
Correct Answer:
True
Which of the following relationships between cost,time,and scope is not realistic?
Free
(Multiple Choice)
4.7/5
(79)
Correct Answer:
A
An activity with a duration of 8 days has an early start time of 25.Another activity has a duration of 5 days and an early start time of 25 days.Both activities precede activity M.Activity M has a duration of 4 days.What is the early start time for activity M?
Free
(Essay)
4.8/5
(75)
Correct Answer:
The first activity will have an early finish time of 33,and the other activity will have an early finish time of 30.Activity M cannot begin while either activity is still being conducted,so it can start at time 33.
This is zero for all of the first activities on a CPM network diagram.
(Multiple Choice)
4.9/5
(97)
List three project management techniques used by corporations or government.
(Essay)
4.9/5
(73)
Additional resources can rarely be used to speed up a project once it is behind schedule.
(True/False)
4.9/5
(78)
In project management,"critical activities" are activities that quality managers must be involved with.
(True/False)
4.8/5
(84)
If an activity has an optimistic time of 5 days,a pessimistic time of 10 days,and a most likely time of 8 days,what is the expected time for the activity?
(Essay)
4.8/5
(69)
A precedence relationship analysis identifies the sequence of activities defined by a work breakdown structure.
(True/False)
4.9/5
(88)
Activity 7 is directly preceded by two activities,activity 5 and activity 6.Activity 5 has an expected time of 5 and ES time of 6.Activity 6 has an expected time of 7 and an ES time of 7.Activity 7 has an expected time of 10.The ES for activity 7 is
(Multiple Choice)
5.0/5
(78)
If a project has an expected completion time of 40 days,with a standard deviation of 2 days,what is the amount of time this project will be completed in,95% of the time?
(Essay)
4.8/5
(81)
Project risk can be grouped into four categories.Which of the following is not one of the categories?
(Multiple Choice)
4.8/5
(81)
Which of the following statements accurately describes the following Gantt chart? 
(Multiple Choice)
4.8/5
(75)
In an AON network diagram,arrows can point to any direction from a node.
(True/False)
5.0/5
(81)
If an activity has an optimistic time of 5 days,a pessimistic time of 10 days,and a most likely time of 8 days,what is the variance for the activity?
(Essay)
4.9/5
(87)
Which project management tool introduces uncertainty into the project planning process?
(Multiple Choice)
4.7/5
(86)
The critical factors in project failure include all of the following except
(Multiple Choice)
4.8/5
(79)
Which of the following examples is not considered a project?