Exam 18: Managing Organizational Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Explain the triple constraint and its importance in project management.

Free
(Essay)
4.9/5
(71)
Correct Answer:
Verified

Project management is the application of knowledge,skills,tools,and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project.The triple constraint includes three interdependent variables-time,scope,and resources.If one changes,they all must change.

Project ______________ are any measurable,tangible,verifiable outcomes,results,or items that are produced to complete a project or part of a project.

Free
(Short Answer)
4.8/5
(69)
Correct Answer:
Verified

Deliverables

A(n)____________ is a temporary endeavor undertaken to create a unique product,service,or result.

Free
(Short Answer)
4.9/5
(72)
Correct Answer:
Verified

Project

What is a project manager?

(Multiple Choice)
4.9/5
(82)

Describe the fundamentals of project management.

(Essay)
4.9/5
(73)

The project management ____________ is an internal department that oversees all organizational projects.

(Short Answer)
4.9/5
(66)

The PMI develops procedures and concepts necessary to support the profession of project management.Which of the following is not one of the three areas it focuses on?

(Multiple Choice)
4.8/5
(83)

A project ____________ is an individual who is an expert in project planning and management,defines and develops the project plan,and tracks the plan to ensure the project is completed on time and on budget.

(Short Answer)
4.8/5
(72)

What is a project?

(Multiple Choice)
4.9/5
(78)

What are project deliverables?

(Multiple Choice)
4.8/5
(90)

Time,cost,and ___________ are the three primary variables in any project.

(Short Answer)
4.8/5
(97)

The project management role has several responsibilities in the area of time.Which of the following answers lists these responsibilities for time?

(Multiple Choice)
4.9/5
(85)

The project management role has several responsibilities in the area of scope.Which of the following answers lists these responsibilities for scope?

(Multiple Choice)
4.8/5
(83)

What is the number one reason that IT projects fall behind schedule or fail?

(Multiple Choice)
4.7/5
(85)

What is a project management office (PMO)?

(Multiple Choice)
4.8/5
(82)

Project management is the application of knowledge,skills,tools,and techniques to project activities to meet project requirements.

(True/False)
4.8/5
(92)

PMI stands for the Project Management Institute.

(True/False)
4.8/5
(73)

Which of the following is a characteristic of a successful project?

(Multiple Choice)
5.0/5
(76)

The project management role has several responsibilities in the area of cost.Which of the following answers lists these responsibilities for cost?

(Multiple Choice)
4.9/5
(74)

The relationships among the triple constraint variables are not dependent.

(True/False)
4.8/5
(93)