Exam 4: Negotiation and the Management of Conflict

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the __________.

(Multiple Choice)
4.8/5
(72)

Negotiating to a __________ solution is the key to conflict resolution in project management.

(Short Answer)
4.8/5
(62)

The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called __________.

(Short Answer)
4.9/5
(73)

Describe the type of relations that generally exist between the organization carrying out the project and a subcontractor working on the project.

(Essay)
4.8/5
(85)

The need to manage technical interfaces and to correct incompatibilities is likely to create technical conflicts during the __________ phase of the project lifecycle.

(Multiple Choice)
4.8/5
(62)

Which of the following is NOT included in the authors' four part agreement for partnering?

(Multiple Choice)
4.8/5
(87)

The __________ approach to negotiation aims to achieve a win-win result.

(Short Answer)
4.9/5
(81)

Toward the end of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to __________.

(Short Answer)
4.8/5
(73)

When dealing with conflict between parties, it is recommended that one __________ in order to avoid the conflict becoming interpersonal.

(Multiple Choice)
4.9/5
(95)

List and describe the three basic causes for change in projects.

(Essay)
4.8/5
(82)

During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to __________.

(Short Answer)
4.9/5
(87)

According to the authors; which of the entities below is NOT a party to the chartering process?

(Multiple Choice)
4.8/5
(77)

Identify the category of conflict that is NOT included in the categories used by Thamhain and Wilemon in their study of project conflict.

(Multiple Choice)
4.8/5
(81)

During project build-up, if a strong matrix organizational form is used, the project manager seeks a commitment of __________ from the functional departments.

(Multiple Choice)
4.8/5
(86)

According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with __________.

(Multiple Choice)
5.0/5
(87)

The __________ approach to negotiation states immediate wants on the assumption that the environment is static.

(Short Answer)
4.9/5
(80)

__________ problems are comparatively rare during project phaseout because most have been solved or bypassed earlier.

(Multiple Choice)
4.8/5
(82)

__________ refers to communications across lines of equivalent authority.

(Short Answer)
4.9/5
(81)

A party to a conflict will usually be satisfied when the level of frustration has been __________.

(Multiple Choice)
4.7/5
(62)

A(n)__________ is simply a written agreement between the PM, senior management, and the functional managers who are committing resources and/or people to the project.

(Short Answer)
4.8/5
(80)
Showing 21 - 40 of 44
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)