Exam 4: Negotiation and the Management of Conflict

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

__________ refers to the modifications to the project plan. In many cases, the projects get larger.

Free
(Short Answer)
4.9/5
(85)
Correct Answer:
Verified

Scope change or scope creep

Describe the four points of principled negotiation described by Fisher and Ury.

Free
(Essay)
4.8/5
(59)
Correct Answer:
Verified

Separate the people from the problem. Focus on interests, not positions. Before trying to reach agreement, invent options for mutual gain. Insist on using objective criteria.

__________ is a method of transforming contractual relationships into a cohesive, cooperative project team with a single set of goals and established procedures for resolving disputes in a timely and effective manner.

Free
(Short Answer)
4.9/5
(77)
Correct Answer:
Verified

Project partnering

__________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.

(Short Answer)
4.9/5
(86)

Personality conflicts during project phase-out are often caused by __________.

(Multiple Choice)
4.8/5
(79)

Which one of the following choices was NOT identified by the authors as one of the reasons why organizations enter into partnership arrangements with each other?

(Multiple Choice)
4.8/5
(90)

One requirement for the conflict/resolution methods described is that they must allow the conflict to be settled without __________ to the project's objectives.

(Essay)
4.9/5
(88)

The authors mention three situations where the highest level of negotiating skill is required by the project manager. Which of the following is NOT one of them?

(Multiple Choice)
4.8/5
(82)

During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving __________.

(Multiple Choice)
4.7/5
(83)

Most of the conflicts that involve the organization and outsiders have to do with __________.

(Multiple Choice)
4.9/5
(90)

Describe the multistep process for building partnered projects.

(Essay)
4.7/5
(86)

Conflicts within the organization typically differ from conflicts with outsiders in one important way. As far as the organization is concerned, these conflicts are __________.

(Multiple Choice)
4.8/5
(77)

During project build-up, the project should move from a general concept to __________.

(Multiple Choice)
4.9/5
(73)

According to the authors, the favored technique for resolving conflict is __________.

(Short Answer)
4.8/5
(80)

The boundaries between departments or functions represent __________.

(Short Answer)
4.7/5
(59)

The general objective of a __________ solution to conflict is to find a solution such that no party can be made better off without making another party worse off by the same amount or more.

(Short Answer)
4.9/5
(83)

Partnering is an attempt to __________ the risk associated with sub-contracting.

(Short Answer)
4.9/5
(90)

Which of the following is NOT one of the four points of principled negotiation?

(Multiple Choice)
4.8/5
(81)

Identify three basic causes for change in projects.

(Essay)
4.7/5
(66)

Identify the three fundamental categories of conflict that occur during a project's lifecycle.

(Essay)
4.8/5
(70)
Showing 1 - 20 of 44