Exam 6: The Work Breakdown Structure and Project Estimation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The final step in determining the cost of an activity is:

(Multiple Choice)
4.9/5
(72)

Project network diagrams provide valuable information about the logical sequence and dependencies among the various activities and tasks so that a completion date or deadline can be determined.

(True/False)
4.9/5
(83)

Assume the following activities for a project along with their estimated durations and predecessors.Describe how critical path analysis would be applied to this project, and calculate the critical path.Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project? Assume the following activities for a project along with their estimated durations and predecessors.Describe how critical path analysis would be applied to this project, and calculate the critical path.Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Once the project schedule and budget are accepted by the client or sponsor, the project plan becomes the baseline plan that will be used as a benchmark to track the project's actual progress.

(True/False)
5.0/5
(67)

The critical path is the longest path in the project network and also is the shortest time in which the project can be completed.

(True/False)
4.8/5
(78)

_____ is considered the most useful and widely used project management tool.

(Multiple Choice)
4.8/5
(81)

What are the benefits and disadvantages of using Gantt charts as a project management tool?

(Essay)
4.9/5
(77)

To make a decision to attempt to build an application system based on what was left after a previous attempt ended in failure primarily because of the large investment the company made in the failed project most likely was made by a manager who did not fully understand:

(Multiple Choice)
4.9/5
(72)

Why should assumptions used in estimating be documented?

(Essay)
4.9/5
(76)

Waiting to leave your shift until another person shows up is an example of:

(Multiple Choice)
4.9/5
(85)

Under the Precedence Diagramming Method, the situation which occurs when task A cannot end until task B starts is called:

(Multiple Choice)
4.9/5
(78)

In what ways are project network diagrams similar to Gantt charts and what additional strengths do they have?

(Essay)
4.9/5
(76)

_____ can help manage the Critical Path by providing information about which activities can be delayed without affecting the deadline target date.

(Multiple Choice)
5.0/5
(76)

Many organizations have a kick-off meeting because

(Multiple Choice)
4.9/5
(69)

The technique used to find the sequence of tasks with zero slack (or float) is most closely associated with:

(Multiple Choice)
4.9/5
(76)

What is the critical chain? How is it different from the concept of a critical path?

(Essay)
5.0/5
(87)

When does the project manager or team have the authority to begin executing the project plan?

(Essay)
4.8/5
(84)

Based upon the following diagram and activity durations, the Critical Path is: Based upon the following diagram and activity durations, the Critical Path is:    Based upon the following diagram and activity durations, the Critical Path is:

(Multiple Choice)
4.9/5
(81)

_____ provide valuable information about the logical sequence and dependencies among the various activities and tasks:

(Multiple Choice)
4.9/5
(86)

Predecessor activities are activities that must be completed before another activity can be started.

(True/False)
4.8/5
(75)