Exam 6: The Work Breakdown Structure and Project Estimation
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
The kick-off meeting brings closure to the planning phase of the project.
Free
(True/False)
4.7/5
(70)
Correct Answer:
True
The cost of labor for using a resource are _____
Free
(Multiple Choice)
5.0/5
(88)
Correct Answer:
A
Three team members are given the task of estimating activity durations.Mr.Optimist estimates the activity to take 2 days to complete.Ms.Pessimist estimates the activity to take 5 days.Mrs.Realist claims that the most likely estimate is 4 days.What should their PERT analysis assign as an expected duration for the activity and what are the benefits and implications of deploying this tool?
(Essay)
4.8/5
(82)
Start-to-Start and Finish-to-Finish relationships allow activities to be worked on in parallel.
(True/False)
4.8/5
(79)
Adding resources to an activity to shorten the critical path is called_____
(Multiple Choice)
4.8/5
(66)
Critical Chain Project Management (CCPM) is based on the idea that
(Multiple Choice)
4.8/5
(86)
_____ can be useful for tracking and monitoring project progress because because they are simple and straightforward.
(Multiple Choice)
4.8/5
(81)
Describe the Precedence Diagramming Method along with the four fundamental relationships that they are based on.
(Essay)
4.7/5
(79)
Describe the five steps that comprise the process of estimating the cost of a particular activity.Illustrate the steps with a hypothetical example.
(Essay)
4.9/5
(79)
Under the Precedence Diagramming Method, the situation which occurs when a relationship between two tasks that can or must start at the same time is called:
(Multiple Choice)
4.8/5
(73)
A reserve can provide a cushion when unexpected situations arise.
(True/False)
4.9/5
(90)
Why should the project manager ensure that the project resources are leveled?
(Essay)
4.9/5
(74)
The direct costs of using a resource is the only type of cost that should be considered when developing the project budget.
(True/False)
4.9/5
(87)
Identifying the critical path is important because a project can only have one critical path and it never changes.
(True/False)
4.8/5
(75)
A start-to-finish activity is the most common relationship between two activities.
(True/False)
4.7/5
(87)
Showing 1 - 20 of 84
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)