Exam 6: The Work Breakdown Structure and Project Estimation
Exam 1: The Nature of Information Technology Projects51 Questions
Exam 2: Project Methodologies and Processes66 Questions
Exam 3: Measurable Organizational Value and the Business Case50 Questions
Exam 4: Project Planning: the Project Infrastructure72 Questions
Exam 5: Project Planning: Scope and the Work Breakdown Structure94 Questions
Exam 6: The Work Breakdown Structure and Project Estimation84 Questions
Exam 7: Managing Project Risk77 Questions
Exam 8: Managing Project Stakeholders and Communication66 Questions
Exam 9: Managing Project Quality60 Questions
Exam 10: Leading the Project Team90 Questions
Exam 11: Managing Organizational Change, Resistance, and Conflict92 Questions
Exam 12: Project Completion79 Questions
Select questions type
An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 days and even under the worst case imaginable, the task would be take 50 days.The estimates PERT duration of that activity is:
(Multiple Choice)
4.9/5
(72)
Installing the operating system on a computer before loading any application packages is an example of:
(Multiple Choice)
4.7/5
(78)
How does the work breakdown structure (WBS) link the project's scope to the schedule and budget?
(Short Answer)
4.8/5
(88)
The amount of time an activity can be delayed before affecting the project deadline is _____
(Multiple Choice)
4.9/5
(78)
Define predecessor, successor, and parallel activities.Give a real world example of each.
(Essay)
4.8/5
(75)
An over allocated resource would arise when Mary is assigned to work on two tasks scheduled at the same time.
(True/False)
4.9/5
(71)
Parallel activities can shorten the project schedule, but can have an impact on project resources if a resource is assigned to two tasks at the same time.
(True/False)
4.9/5
(68)
Identifying the critical path is important because any change in the duration of the activities or tasks on the critical path will affect the project's schedule.
(True/False)
4.9/5
(71)
Starting the next task before the first task is complete is _____
(Multiple Choice)
4.9/5
(70)
Describe the steps necessary for estimating the cost of a particular activity or task that has an estimated duration.
(Essay)
5.0/5
(84)
Scheduling other projects so that resources may be shared is_____
(Multiple Choice)
4.8/5
(92)
Rent, utilities, insurance and administrative costs are examples of:
(Multiple Choice)
5.0/5
(93)
Define the following and give a real world example of each (other than the ones described in this book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.
(Essay)
4.9/5
(82)
Sunk costs include such things as rent, utilities, insurance, and other administrative costs.
(True/False)
5.0/5
(80)
The critical path is the shortest path in the project network and also is the longest time in which the project can be completed.
(True/False)
4.8/5
(76)
Showing 41 - 60 of 84
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)