Exam 12: Purchasing and Supply Chain Analysis: Tools and Techniques

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity time.

(Multiple Choice)
5.0/5
(78)

In a PERT network, a/an _____ is the earliest point in time an activity can begin.

(Multiple Choice)
4.7/5
(80)

[A] _____ establishes the rate of improvement because of learning as producers realize direct-labor cost improvements as production volumes increase.

(Multiple Choice)
4.8/5
(86)

A/An _____ consists of activities or steps that can be performed at the same time during the main flow of work. ​

(Multiple Choice)
4.9/5
(80)

Each activity in PERT has three time estimates: (1) most likely, (2) pessimistic, and (3) optimistic.

(True/False)
4.9/5
(82)

In value stream mapping, the flow diagram that depicts the process and shows the times and resources used at each step and the time delay between each step is called a/an _____.

(Multiple Choice)
4.8/5
(72)

_____ is a technique used to examine the incremental changes in cost between quantities within a supplier's price quotation.

(Multiple Choice)
4.8/5
(85)

All of the following are points that should be considered before initiating a project except _____.

(Multiple Choice)
4.8/5
(90)

Users apply _____ to projects where there is a single known time for each activity with no variance, while _____ applies to projects where time estimates are variable or uncertain.

(Multiple Choice)
4.9/5
(84)

All processes or items can benefit from, or exhibit improvement from, learning.

(True/False)
4.9/5
(72)

In a PERT network, the difference between the _____ and the _____ is slack.

(Multiple Choice)
4.8/5
(85)

Which of the following is not a question that value analysis teams should ask to determine if opportunities exist for item, product, or service improvement?​

(Multiple Choice)
4.8/5
(69)

_____ is a process of visually presenting the flow of materials and information to identify wasted time and actions in a manufacturing or service process.

(Multiple Choice)
4.7/5
(81)

In value stream mapping, the flow diagram that depicts process improvements to optimize the value and minimize the non-value-added streams is called a/an _____.

(Multiple Choice)
4.8/5
(92)

According to Ohno and Toyota, _____ is a category of waste that uses more steps to produce a product than necessary.

(Multiple Choice)
4.8/5
(79)

Most processes do not cross functional boundaries.

(True/False)
4.8/5
(73)

The primary objective of value analysis is to increase the value of an item or service at the lowest cost without sacrificing quality.

(True/False)
4.9/5
(87)

In a CPM or PERT project, a network is a graphical representation that shows how each individual activity relates in time and sequence to all other activities.

(True/False)
4.9/5
(83)

Which of the following is Falseregarding when to use the learning curve?​

(Multiple Choice)
4.9/5
(77)

According to Ohno and Toyota, _____ is a category of waste that occurs when employees are standing about and inventory is at a standstill.

(Multiple Choice)
5.0/5
(86)
Showing 41 - 60 of 67