Exam 12: Project Management
Exam 1: Introduction to Supply Chain and Operations Management67 Questions
Exam 2: Supply Chain and Operations Strategy80 Questions
Exam 3: Product and Process Design and Mapping89 Questions
Exam 4: Service Design96 Questions
Exam 5: Customer Relationship Management52 Questions
Exam 6: Strategic Sourcing78 Questions
Exam 7: Supplier Management59 Questions
Exam 8: Demand Management and Forecasting75 Questions
Exam 9: Inventory Management Fundamentals and Independent Demand84 Questions
Exam 10: Sales and Operations Planning and Enterprise Resource Planning110 Questions
Exam 11: Logistics94 Questions
Exam 12: Project Management90 Questions
Exam 13: Supply Chain Quality Management84 Questions
Exam 14: Statistical Process Control74 Questions
Exam 15: Lean and Six Sigma Management and Leading Change76 Questions
Select questions type
Adding on unnecessary deliverables to a project is known as ________.
(Short Answer)
4.9/5
(67)
The latest starting time for a task is equal to the latest finish time minus the task time.
(True/False)
4.9/5
(76)
Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks
Most likely completion time = 4 weeks
Pessimistic completion time = 7 weeks
Compute the expected time for the task.
(Multiple Choice)
4.9/5
(81)
A tool for prioritizing potential projects where an estimate is made of the difficulty of completing the project in a reasonable amount of time with available resources is known as ________.
(Short Answer)
4.9/5
(80)
Specialists that are assigned full-time to a project that needs to be completed quickly are known as ________ team(s).
(Short Answer)
4.7/5
(83)
A graph that conceptually shows how cumulative costs are incurred during a project over time is known as the ________.
(Short Answer)
4.9/5
(82)
The shortest time for completing a project task is known as ________.
(Short Answer)
4.9/5
(83)
________ is a term applied to the process of managing changes to the project charter and plan.
(Short Answer)
4.9/5
(70)
The best estimate for the time required to complete a project task is known as ________.
(Short Answer)
4.8/5
(82)
Task C is directly preceded by two tasks-task A and task B.Task A has an expected task completion time of five weeks and an ES time of week 6.Task B has an expected task completion time of seven weeks and an ES time of week 7.Task C has an expected task completion time of 10 weeks.The ES for activity C is week
(Multiple Choice)
4.8/5
(75)
A sequence of activities that leads from the starting node to the finishing node is called a
(Multiple Choice)
4.9/5
(79)
Scheduling production on a weekly basis is an example of a project.
(True/False)
4.9/5
(88)
The act of determining which tasks precede and follow other tasks is known as ________.
(Short Answer)
4.7/5
(78)
The phase of the project in which the rate of spending typically increases is the planning phase.
(True/False)
4.7/5
(80)
Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? 
(Multiple Choice)
4.8/5
(70)
Key phases in a project time line are often referred to as milestones.
(True/False)
4.7/5
(78)
A tool for monitoring who is assigned to multiple projects is known as ________.
(Short Answer)
4.8/5
(90)
The project charter is most likely to include the project goals,scope and deliverables.
(True/False)
4.8/5
(85)
Reporting to see that the project plan is being followed is a key activity during which phase of a project?
(Multiple Choice)
4.7/5
(75)
The project team stage of development when a mutually supportive,steady state is achieved is
(Multiple Choice)
4.8/5
(70)