Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? 
A) 13
B) 16
C) 20
D) 24
Correct Answer:

Verified
Correct Answer:
Verified