Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
Consider the following table of activities that describes a project network. How much reduction in project duration could you get from crashing activity C?
(Multiple Choice)
5.0/5
(92)
Direct costs are assignable directly to a particular ________.
(Multiple Choice)
4.9/5
(69)
The shortest possible time an activity can be completed realistically is called ________ time.
(Multiple Choice)
4.9/5
(84)
The total cost for each time unit of a project is the sum of labor, materials, and equipment.
(True/False)
4.7/5
(80)
Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.
(Multiple Choice)
4.9/5
(72)
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?
(Multiple Choice)
4.9/5
(77)
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by
(Multiple Choice)
4.9/5
(85)
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?
(Multiple Choice)
4.9/5
(77)
When you schedule ________ exclusively, you avoid the additional costs of coordination and communication when new people are added.
(Multiple Choice)
4.8/5
(79)
Which of the following is not likely to result in an imposed deadline?
(Multiple Choice)
5.0/5
(82)
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
(True/False)
4.9/5
(84)
The higher the cost slope of an activity the lower the cost to reduce its duration.
(True/False)
4.8/5
(83)
The direct cost for completing an activity as early as possible is called its ________ cost.
(Multiple Choice)
4.8/5
(88)
Which of the following projects would be least benefited if additional resources were added?
(Multiple Choice)
4.8/5
(78)
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of
(Multiple Choice)
4.9/5
(77)
Crashing activities on a project network that is sensitive could increase the risk of the project being late.
(True/False)
4.7/5
(93)
All of the following are disadvantages of scheduling overtime EXCEPT
(Multiple Choice)
4.8/5
(87)
How would you calculate an activity's slope and what does it represent?
(Essay)
4.9/5
(75)
Consider the following table of activities that describes a project network. After all the crashing you can do is done (assuming you can crash only one activity at a time), how many paths are critical? Which activities remain noncritical? Would you characterize this network as sensitive or insensitive?
(Multiple Choice)
4.8/5
(74)