Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider the following table of activities that describes a project network. How much reduction in project duration could you get from crashing activity C?

(Multiple Choice)
5.0/5
(92)

An insensitive project network has the benefit of:

(Multiple Choice)
4.9/5
(64)

Direct costs are assignable directly to a particular ________.

(Multiple Choice)
4.9/5
(69)

The shortest possible time an activity can be completed realistically is called ___­­­_____ time.

(Multiple Choice)
4.9/5
(84)

The total cost for each time unit of a project is the sum of labor, materials, and equipment.

(True/False)
4.7/5
(80)

Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

(Multiple Choice)
4.9/5
(72)

When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?

(Multiple Choice)
4.9/5
(77)

Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by

(Multiple Choice)
4.9/5
(85)

Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

(Multiple Choice)
4.9/5
(77)

When you schedule ________ exclusively, you avoid the additional costs of coordination and communication when new people are added.

(Multiple Choice)
4.8/5
(79)

Which of the following is not likely to result in an imposed deadline?

(Multiple Choice)
5.0/5
(82)

Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.

(True/False)
4.9/5
(84)

The higher the cost slope of an activity the lower the cost to reduce its duration.

(True/False)
4.8/5
(83)

The direct cost for completing an activity as early as possible is called its ________ cost.

(Multiple Choice)
4.8/5
(88)

Which of the following projects would be least benefited if additional resources were added?

(Multiple Choice)
4.8/5
(78)

When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of

(Multiple Choice)
4.9/5
(77)

Crashing activities on a project network that is sensitive could increase the risk of the project being late.

(True/False)
4.7/5
(93)

All of the following are disadvantages of scheduling overtime EXCEPT

(Multiple Choice)
4.8/5
(87)

How would you calculate an activity's slope and what does it represent?

(Essay)
4.9/5
(75)

Consider the following table of activities that describes a project network. After all the crashing you can do is done (assuming you can crash only one activity at a time), how many paths are critical? Which activities remain noncritical? Would you characterize this network as sensitive or insensitive?

(Multiple Choice)
4.8/5
(74)