When a Project Manager Must Reduce Project Duration but Resources

Question 76

Multiple Choice

When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of


A) fast-tracking.
B) use critical-chain project management.
C) reduce project scope.
D) compromise quality.
E) do it twice-fast and correctly.