Multiple Choice
An insensitive project network has the benefit of:
A) Not increasing risk as activities are initially crashed.
B) Having potential for real cost savings when crashed.
C) Having potential for significant time savings when crashed.
D) Having potential for flexible scheduling.
E) All of these alternatives are correct.