Exam 13: Material Requirements Planning Mrp and Erp
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
The time-phased product structure, unlike the bill of material, adds the concept of lead times.
(True/False)
4.8/5
(79)
In MRP, the number of units projected to be available at the beginning of each time period refers to:
(Multiple Choice)
4.9/5
(82)
Audrey Ross, operations manager for BCD Technologies, must schedule work for the next five days. Each unit takes 20 minutes to process. Available capacity is 8 hours per day. The production order quantities are 18, 28, 38, 16, and 20 for Monday through Friday, respectively. What should be the plan for Wednesday?
(Multiple Choice)
4.8/5
(78)
By convention, what is the top level in a product structure?
(Multiple Choice)
4.9/5
(83)
________ strategically alters lead times and precisely places safety stock within the BOM structure to improve MRP performance.
(Short Answer)
4.9/5
(87)
Planning bills of material are bills of material for "kits" of expensive items such as CPUs and motherboards.
(True/False)
4.8/5
(73)
A manufacturing company is trying to determine the cost of materials used to produce an A. If Ds cost $3 and Fs cost $5, how much does it cost to produce an A (in D and F materials only)?

(Essay)
4.9/5
(80)
Product A is made from 2 Bs and 1 C. Lead times for A, B, and C are 2, 1, and 2 weeks respectively. Currently there are 2 Bs and 5 Cs on hand, with 5 of each scheduled to arrive at the end of week 1. If 20 As are needed during week 3, can the order be completed (it is the start of week 0 currently)?
(Essay)
4.9/5
(86)
________ are the result of adjusting gross requirements for inventory on hand and scheduled receipts.
(Essay)
5.0/5
(92)
A grill assembly takes 20 washers. Instead of listing these washers separately, they are grouped into a single kit for production. How is the bill of material for the washers classified?
(Multiple Choice)
4.9/5
(76)
Wheeled Coach uses ________ as the catalyst for low inventory, high quality, tight schedules, and accurate records.
(Short Answer)
4.8/5
(66)
What lot-sizing technique is generally preferred when inventory holding costs are extremely high?
(Multiple Choice)
4.8/5
(70)
A material requirements plan contains information with regard to all of the following EXCEPT:
(Multiple Choice)
5.0/5
(82)
If X consists of one A and one B, and each A consists of one F and two Gs, then A is the "parent" component of G.
(True/False)
4.9/5
(75)
The quantity required of a dependent demand item is computed from the demand for the final products in which the item is used.
(True/False)
4.8/5
(86)
Explain the difference between a gross requirements plan and a net requirements plan.
(Essay)
4.9/5
(80)
Smoothing a resource requirements profile to stay within capacity limits may increase setup costs.
(True/False)
4.9/5
(81)
Showing 41 - 60 of 133