Exam 8: Flexible Budgets and Variance Analysis

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Standard cost systems value products according to actual costs.

(True/False)
4.9/5
(81)

Identify which statement below about "currently attainable standards" is not true.

(Multiple Choice)
4.7/5
(91)

A static budget is another name for the _____budget.

(Multiple Choice)
4.9/5
(85)

Actual results might differ from the static budget because _____.

(Multiple Choice)
4.9/5
(80)

Variances are signals that actual operations are different from what was anticipated.

(True/False)
4.9/5
(75)

The Long Company makes tables for which the following standards have been developed: Standard Inputs Standard Frice Expected for Each Expected per Unit of Output Unit of Output Direct materials 12 pounds \ 4 per pound Direct labor 4 hours \ 30 per hour Production of 200 tables was expected in August, but 220 tables were actually completed. Direct materials purchased and used were 2,100 pounds at an actual price of $4.40 per pound.Direct-labor cost for the month was $10,620, and the actual pay per hour was $18.00._____ is the standard labor cost for each table produced.

(Multiple Choice)
4.8/5
(81)

Black Company planned to produce and sell 900 units at a total cost of $180,000.Actual production was 900 units at a cost of $170,000, Black Company was _____.

(Multiple Choice)
4.7/5
(82)

Identify which statement below would not be a possible reason for a variance between a flexible budget and actual results.

(Multiple Choice)
4.7/5
(81)

The Foot Company currently produces sandals in an automated process. Expected produc?tion per month is 20,000 units.The required direct materials cost is $1.50 per unit.Manufacturing fixed overhead costs are $30,000 per month.Manufac?turing overhead is allocated based on units of production._____ is the flexible budget for 15,000 and 20,000 units, respectively.

(Multiple Choice)
4.8/5
(83)

A price variance is favorable if _____.

(Multiple Choice)
4.8/5
(77)

Actual output in units measured in standard direct-labor hours

(Short Answer)
4.7/5
(77)

The overhead efficiency variance indicates to management how much overhead cost it may waste by not controlling the use of cost-driver activity.

(True/False)
4.9/5
(88)

This is another name for the flexible budget

(Short Answer)
4.9/5
(78)

If the total sales-activity variance was $8,000 favorable, and the total static-budget variance was $10,000 favorable, then the total flexible-budget variance must have been:

(Multiple Choice)
4.9/5
(82)

Sales-activity variances measure how efficient managers have been in meeting the planned sales objective.

(True/False)
4.9/5
(70)

The following data for the Popular Company pertain to the produc?tion of 2,000 clay pigeons during July: Standard variable-overhead cost was $6.00 per pound of clay. Total actual variable-overhead cost was $18,200. Standard variable-overhead cost allowed for units produced was $20,000. Variable overhead-efficiency variance was $740 unfavorable. _____ is standard direct-material amount per clay pigeon.

(Multiple Choice)
4.8/5
(85)

The most recent operating budget for Skipper Company is based on production of 42,000 units with 1.0 machine hour allowed per unit.Variable manufacturing overhead is anticipated to be $20 per unit.Actual production was 45,000 units using 40,000 machine hours.Actual variable cost was $725,000. Required: Compute the commonly used variances for a variable over?head report.Do not prepare the report.

(Essay)
4.8/5
(60)

The Cheers Company makes mugs for which the following standards have been developed: Standard Inputs Standard Frice Expected for Each Expected per Unit of Output Unit of Output Direct materials 5 ounces \ 2 per ounce Direct labor 1.5 hours \ 8 per hour Production of 400 mugs was expected in July, but 440 mugs were actually completed. Direct materials purchased and used were 2,100 ounces at an actual price of $2.20 per ounce.Direct-labor cost for the month was $5,310, and the actual pay per hour was $9.00._____ is the direct-material quantity variance for July.

(Multiple Choice)
4.9/5
(94)

Actual price - standard price) x actual quantity of labor

(Short Answer)
4.9/5
(85)

Flat Company currently produces cardboard boxes in an automated process.Expected produc?tion per month is 40,000 units.The required direct materials cost $0.30 per unit.Manufacturing fixed overhead costs are $24,000 per month.Manufacturing overhead is allocated based on units of production.____ is the flexible budget for 40,000 and 20,000 units, respectively.

(Multiple Choice)
4.9/5
(79)