Exam 4: Budgeting the Project
Exam 1: The World of Project Management65 Questions
Exam 2: The Manager, the Organization, and the Team60 Questions
Exam 3: Planning the Project56 Questions
Exam 4: Budgeting the Project61 Questions
Exam 5: Scheduling the Project67 Questions
Exam 6: Allocating Resources to the Project70 Questions
Exam 7: Monitoring and Controlling the Project68 Questions
Exam 8: Evaluating and Terminating the Project71 Questions
Select questions type
The first unit requires 10 hours to complete. If the industry uses an 80 percent learning rate, how long should the third unit take?
(Multiple Choice)
4.9/5
(80)
The best approach to handling change in projects is to accept the negative change and take a loss on the project.
(True/False)
4.8/5
(73)
The name given to the budget process that aggregates income and expenditures across projects is:
(Multiple Choice)
4.7/5
(83)
Victoria, an artisan who produces handcrafted furniture, has to carve six ornate chairs to go around a table. It takes her 10 hours to complete the first chair. She estimates that her learning rate is 80 percent. Given this information, Victoria should be able to make the second chair in _____.
(Multiple Choice)
4.7/5
(74)
Top-down budgeting typically results in better acceptance of the budget.
(True/False)
4.8/5
(85)
After major risk are identified which of the following data should NOT be obtained for analysis
(Multiple Choice)
4.9/5
(78)
Mechanical tasks typically have higher learning rates than more mental tasks.
(True/False)
4.9/5
(67)
Rachel, a project manager, has undertaken a project to build a wall around a compound. She estimates that the cost of materials will be $520 and labor costs will be $10 for 20 hours. If the overheads for this project are 50 percent of the labor and material costs, the total cost will be:
(Multiple Choice)
4.8/5
(86)
The budgeting approach based on the collective judgments of top and middle managers is called:
(Multiple Choice)
4.9/5
(95)
There is a 30 percent chance that a new product development project will result in sales of $500,000 and a 70 percent chance that the project will result in sales of $100,000. What is the expected value of this project?
(Multiple Choice)
4.8/5
(78)
Explain how you would use the shape of a project's life cycle to resolve budget conflicts between a superior and subordinate.
(Essay)
4.7/5
(73)
As a project unfolds, the cost uncertainty increases as the project moves towards completion.
(True/False)
4.8/5
(79)
Activity budgets show expenses by task and expected time period of the expenditure.
(True/False)
4.8/5
(73)
Briefly explain how learning curves can help improve the cost estimating process.
(Essay)
4.8/5
(76)
Bottom-up budgets are usually more accurate in the detailed tasks.
(True/False)
4.9/5
(75)
Devon, a project manager, is working on a software development project. He needs more coders to complete the project on time. As a result, he hires people and they are given on-the-job training by their coworkers. However, this significantly reduces the output of the team and leads to a delay in the project. The given scenario exemplifies:
(Multiple Choice)
4.8/5
(86)
By very careful planning, a project manager can do away with cost uncertainty.
(True/False)
4.8/5