Crashing non-critical activities will influence project duration.

Free
(True/False)
4.8/5
(81)
Correct Answer:
Verified

False

One limitation of Microsoft Project is that all resources must share the same availability calendar.

Free
(True/False)
4.7/5
(72)
Correct Answer:
Verified

False

Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?

Free
(Multiple Choice)
4.8/5
(86)
Correct Answer:
Verified

C

The practice of assigning project team members to multiple projects is called…

(Multiple Choice)
4.7/5
(68)

When crashing a task, the usual assumption is that a task is crashed the full amount or none at all.

(True/False)
4.8/5
(79)

The CPM method cannot be used when task durations are probabilistic.

(True/False)
4.7/5
(76)

Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?

(Multiple Choice)
4.8/5
(92)

All of the following are criteria available to help choose the priority rule mentioned in the textbook except;

(Multiple Choice)
4.9/5
(67)

Victoria, a project manager, has undertaken a project similar to one she did earlier. Owing to her team's familiarity with the processes that are required to complete the project, Victoria is able to produce the required deliverable ahead of schedule. She achieves this by simultaneously completing two phases of work. In this scenario, which of the following does Victoria use to complete the project?

(Multiple Choice)
4.7/5
(83)

A task's duration is a function of both the amount of labor required to complete the task as well as the calendar time required to complete it.

(True/False)
4.9/5
(81)

Starting the building phase before the design and planning phases is called…

(Multiple Choice)
4.9/5
(80)

Alice, a project manager, has undertaken a project to build an irrigation canal. Based on the resources allocated to her, she makes an initial estimate that the time required to dig the canal would be 20 days. She also prepares an alternative estimate by adding an additional resource that will allow the project to be completed in 10 days. This alternative estimate that Alice prepares is referred to as the _____.

(Multiple Choice)
4.9/5
(73)

A project that must be completed within the specified performance requirements is considered…

(Multiple Choice)
4.9/5
(74)

Arthur, a project manager, has multiple projects under him, and his team members are multitasking between these projects. When he planned these projects, Arthur asked his team members the number of hours they will take to complete their respective tasks. However, they are taking longer than discussed, which is preventing Arthur from taking on more projects. According to Goldratt, which of the following should Arthur do to fix this issue?

(Multiple Choice)
4.9/5
(75)

For resources that are consumed when used, the problem is which project gets to use the resource first and which must wait.

(True/False)
4.8/5
(73)

Explain how you would choose a priority rule.

(Essay)
4.8/5
(68)

The safety time added to chains other than the critical chain is called…

(Multiple Choice)
4.9/5
(79)

The as late as possible priority rule is considered the standard scheduling rule.

(True/False)
4.9/5
(72)

When the work is routine, fast-tracking rarely causes serious problems.

(True/False)
4.8/5
(74)

Allocating specific, limited resources to specific activities is called…

(Multiple Choice)
4.9/5
(74)