Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.

(True/False)
4.8/5
(93)

Each organization or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is responsible.

(True/False)
4.9/5
(88)

The estimated types and quantities of resources required for an activity together with the availability of those resources will influence the

(Multiple Choice)
4.8/5
(89)

The ____ and ____ times are determined by calculating forward through the network.

(Multiple Choice)
4.9/5
(79)

The ____ and ____ times are determined by working through the network diagram from the end of the project to the beginning of the project.

(Multiple Choice)
4.7/5
(79)

Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(69)

In most cases, eliminating negative slack by reducing durations of activities will involve a trade-off in the form of an increase in ____ or a reduction in ____.

(Multiple Choice)
4.9/5
(82)

Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

(Multiple Choice)
4.7/5
(74)

Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(85)

Playing the game of inflating estimated durations in anticipation of the project manager negotiating shorter durations is a good practice.

(True/False)
5.0/5
(80)

The ____ is the estimated cost to complete the activity in the crash time.

(Multiple Choice)
4.8/5
(89)

The key to effective project control is

(Multiple Choice)
4.7/5
(78)

If the planned corrective actions do not result in an acceptable schedule, then

(Multiple Choice)
4.9/5
(80)

It is a good practice to have the person who will be responsible for performing activities in a project estimate the duration for other activities to be completed by other resources although the person might not have experience with those activities.

(True/False)
4.7/5
(89)

Latest start time (LS)is the latest time by which a specific activity must be

(Multiple Choice)
4.8/5
(84)

If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time.

(Multiple Choice)
4.8/5
(72)

Each time the schedule is recalculated in the project, the schedule should be

(Multiple Choice)
4.9/5
(75)

The project team can progressively elaborate the estimated durations as more information is known or becomes clear to allow for more accurate estimated durations.

(True/False)
4.9/5
(82)

Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated occurrence.

(True/False)
4.9/5
(78)

The estimated activity resources will also be used later for estimating activity costs and determining the project budget.

(True/False)
4.7/5
(98)
Showing 61 - 80 of 127
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)