Exam 7: Determining Costs, Budget and Earned Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.

(Multiple Choice)
4.9/5
(77)

At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy.This is especially true for

(Multiple Choice)
5.0/5
(98)

The two-step process for budgeting is

(Multiple Choice)
4.8/5
(75)

When the CPI goes below 1.0 or gradually gets smaller, corrective action should not be taken, the project is performing well.

(True/False)
4.9/5
(64)

The cost performance analysis should include identifying those work packages that have a negative cost variance or a cost performance index of less than ____.

(Multiple Choice)
4.8/5
(72)

The worst scenario from the contractor's point of view is to have the customer make only one payment at the end of the project.

(True/False)
5.0/5
(85)

Committed costs are also known as discharged or postponed costs.

(True/False)
4.9/5
(64)

___ is the difference between the cumulative earned value of the work performed and the cumulative actual cost.

(Multiple Choice)
4.8/5
(72)

The total budgeted cost for the project is

(Multiple Choice)
4.9/5
(73)

Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the ____ of the work package by the percent complete.

(Multiple Choice)
4.9/5
(80)

Which of the following is not a way to reduce the costs of activities:

(Multiple Choice)
4.8/5
(86)

The contractor might try to negotiate payment terms that require the customer to do one or more of the following except

(Multiple Choice)
4.8/5
(82)

Once the project starts, it is necessary to keep track of actual cost and committed cost so that they can be compared to the ____.

(Multiple Choice)
4.8/5
(86)

Another indicator of cost performance is cost variance (CV).If the cumulative earned value is greater than the cumulative actual costs, then

(Multiple Choice)
4.8/5
(80)

The key to managing a cash flow is to

(Multiple Choice)
4.8/5
(84)

The ____ is the amount that was budgeted to accomplish the work that was schedule to be performed up to that point in time.

(Multiple Choice)
4.9/5
(82)

____ involves the following: Analyzing cost performance to determine which work packages may require corrective action; Deciding what specific corrective action should be taken; and Revising the project plan, including time and cost estimates, to incorporate the planned corrective action.

(Multiple Choice)
4.9/5
(76)

For a project, the TBC = $200,000, the CEV = $100,000, the CAC = $120,000.Which of the following statements is true?

(Multiple Choice)
4.9/5
(90)

What is the cost variance for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.

(Multiple Choice)
4.8/5
(89)

A cost performance index greater than 1.0 means

(Multiple Choice)
4.8/5
(84)
Showing 61 - 80 of 103
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)