If the labour efficiency variance is unfavourable, then
A) actual hours exceeded standard hours allowed for the actual output.
B) standard hours allowed for the actual output exceeded actual hours.
C) the standard rate exceeded the actual rate.
D) the actual rate exceeded the standard rate.