Multiple Choice
The following standards for variable manufacturing overhead have been established for a company that makes only one product:Standard hours per unit of output 7.0 hours
Standard variable overhead rate £ 11.35 per hour
The following data pertain to operations for the last month:
- What is the materials quantity variance for the month?
A) £9,940 U
B) £15,351 U
C) £14,484 U
D) £10,535 U
Correct Answer:

Verified
Correct Answer:
Verified