Cox Engineering Performs Cement Core Tests in Its Laboratory During March, the Laboratory Performed 2,000 Core Tests
Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of £7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of £8,610.
Actual variable manufacturing overhead incurred was £3,200.
-The labour rate variance for March is
A) £4,578 unfavourable.
B) £1,470 unfavourable.
C) £4,578 favourable.
D) £1,470 favourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q25: Perkins Company, which has a standard
Q26: The standard cost per unit is computed
Q27: List the disadvantages of standard costing.
Q28: A labour efficiency variance resulting from the
Q29: The following materials standards have been
Q31: Cox Engineering performs cement core tests
Q32: Standard costs greatly increase the complexity of
Q33: The entry to record an unfavorable material
Q34: The Geurtz Company uses standard costing. The
Q35: If the labour efficiency variance is unfavourable,