Question 41
Multiple Choice
The best sources of items to be monitored are the project risk management plan,change of scope orders,and __________.
Question 42
Multiple Choice
Reports for __________ have a need for detailed information about individual tasks and the factors affecting such tasks.
Question 43
Multiple Choice
If EV = $500,AC = $475,PV = $450; SV = ________.
Question 44
Multiple Choice
__________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.
Question 45
Multiple Choice
A(n) __________ is a simple tally of the occurrence of an event.This type of measure is easy to collect and is often reported as events per unit of time or reported as events as a percent of a standard number.
Question 46
Multiple Choice
If CSI is less than 1,it is indicative of a(n) __________.
Question 47
Multiple Choice
In earned value analysis,the 50-50 rule assumes that __________.
Question 48
Multiple Choice
If CPI = 1.05,then __________ is favorable.
Question 49
Multiple Choice
In earned value analysis,the 0 - 100 percent rule allows __________.
Question 50
Multiple Choice
__________ is collecting,recording,and reporting information concerning any and all aspects of project performance that the project manager or others in the organization wish to know.
Question 51
Multiple Choice
Measuring characteristics such as "quality of team member cooperation" and "morale of team members" generally takes the form of __________characterizations.
Question 52
Multiple Choice
The project control process should be viewed as a(n) __________,with revised plans and schedules (if warranted) following corrective actions.The project control process should run continuously until the project is completed.