Question 61
Multiple Choice
The assignment method is useful in solving scheduling problems that have which of the following characteristics?
Question 62
Multiple Choice
Which of the following is one of the major functions of shop-floor control?
Question 63
Multiple Choice
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete) , B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.Which job should be scheduled first if you use the SOT priority rule for job sequencing?
Question 64
Short Answer
A work center has five jobs assigned to it.They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, andE.The work center may work on only one job at a time and must complete any job it starts before starting another job.Job A has a processing time of 6 days and is due to the customer in 9 days.Job B has a processing time of 2 days and is due in 16 days.Job C has a processing time of 4 days and is due in 10 days.Job D has a processing time of 3 days and is due in 7 days.Job E has a processing time of 5 days and is due in 12 days.Using the first-come, first-served priority rule, in what order should these jobs be undertaken? ___________________________________.
Question 65
Multiple Choice
Which of the following is not a priority rule used to schedule the sequence of jobs in a production operation?
Question 66
True/False
In finite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
Question 67
True/False
In infinite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
Question 68
Essay
In the context of work assignment, what is infinite loading? ___________________________________________.
Question 69
True/False
Theoretically, all schedules are feasible when finite loading is used.
Question 70
Multiple Choice
Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations, with the smallest value being run first?