Question 1
Multiple Choice
The unit improvement factor for an 80 percent learning curve at 100 units is 0.2271.The first and second timings of a person doing a job are 20 minutes and 16 minutes, respectively.What is the learning-adjusted time estimate for unit number 100?
Question 2
True/False
You time someone completing a single task the first time at 10 minutes, and the second time they do the task it takes 9 minutes.You should use an 80 percent learning curve to estimate the length of time this worker will take to complete this task in the future.
Question 3
Multiple Choice
Which of the following is a reason that there are disparities between a firm's learning curve rate and that of its industry?
Question 4
Short Answer
If a person performing a task has been achieving an 85 percent learning curve and if it took 1 minute to produce the first unit, what will be the total time to produce 1,000 units? ______________________
Question 5
True/False
A learning curve is a line displaying the relationship between unit production time and the cumulative number of units produced.
Question 6
True/False
A learning curve shows the increase in time required for each successive unit completed.
Question 7
Multiple Choice
You have just timed a person doing a hair cut for the first time.It took 50 minutes.What unit improvement factor learning curve would you use if the person took 35 minutes on the second hair cut?
Question 8
True/False
A learning curve is a line displaying the way unit production time decreases as time passes.
Question 9
True/False
The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933.The first and second timings of a person doing a job are 10 minutes and 6 minutes, respectively.The learning-adjusted time estimate for the unit number 25 is 0.9330 minute.
Question 10
Multiple Choice
The 10
th
repetition of job is timed at 100 minutes.If the learning curve for this job is 80 percent, what is the estimated time for the 100
th
repetition of this job?
Question 11
Multiple Choice
You have just timed a person doing a job a few times.The first time it took the person 25 minutes, the second time it took 20 minutes, and the third time it took 17.55 minutes.Which learning curve unit improvement factor should you use?